14
5.3.1 Boiler drum installation
1. Put the boiler drum on an embedding.
2. Put a sealing
φ
90 x 60 x 3 on the upper flange part of the back section and fix the flange of the heat
water. The flange to be welded to the distribution of the heat water in advance.
3. Put a sealing
φ
90 x 60 x 3 on the bottom flange part of the back section and fix the flange of the
returnable water with a socket for impregnating and clearing plug. The flange to be welded to the
distribution of the returnable water in advance.
4. An elbow with an impregnating and clearing plug to be screwed to the flange socket of the returnable
water after connection of the furnace to the heat system
5. To put the stove – pipe to the smoky chimney - pot and penetrate it into the chimney hole
6. To screw the draught controller to the hole in the upper part of the front section
7. Two holes with a Js 6/4“ thread in the front section to blind with Js 6/4“ closures
1. Sealing
φ
90 x 60 x 3
2. Heating water flange
3. Washer10,5
4. Nut
M10
5. Sealing
φ
90 x 60 x 3
6. Return
water
flange
7. Washer
10,5
8. Nut
M10
9. Filling and draining cock
Fig. Nr. 10 Boiler drum installation