Vertiv™ NetSure™ -48 VDC Battery Rack System Installation and User Manual
Proprietary and Confidential © 2022 Vertiv Group Corp.
13
7
Initially Starting the System
Procedure
1.
Ensure all furnished protective covers are installed.
2.
Turn ON the battery disconnect circuit breakers (located on the front of the box framework, adjacent to each battery tray).
NOTE!
Circuit breakers are provided with lockout/tagout capability.
3.
Refer to any initial startup procedure in the documentation supplied with the associated power system.
8
Maintenance
8.1
Batteries
For battery maintenance procedures, refer to the manual provided with the batteries.
8.2
System Maintenance Procedures
It is recommended to perform the maintenance procedures listed in Table 8.1
every 6-months to ensure continual system operation.
Table 8.1 Maintenance Procedures to be performed at 6-Month Intervals
PROCEDURE
REFERENCED IN
Inspect and tighten all installer's connections.
“Making Electrical Connections” section on page 5.
9
Troubleshooting and Repair
9.1
Contact Information
Refer to Section 4154 (provided with your customer documentation) for support contact information.
9.2
Batteries
For battery troubleshooting and repair procedures, refer to the manual provided with the batteries.