3.
Install the frame ground landing point adapter P/N 556872 to the left or right side of the battery cabinet,
as shown in
Figure 5:
Installing P/N 556872 Frame Ground Landing Point Adapter
4.
Mount the battery cabinet to a wall through the two 0.406” diameter holes on the back of the cabinet, as
shown in
. If mounting to a stud wall, secure the battery cabinet to the studs.
5.
Ensure the technique and hardware used in securing the cabinet can support the total weight of the
cabinet and the batteries. Refer to “Batteries” on page 9 for a battery weight reference table.
Frame Grounding Point
(1/4-20 Studs on 5/8” Centers)
(Torque to 75 in-lbs)
Attach Frame Ground Landing
Point Adapter to Cabinet
(Torque to 46 in-lbs)