Figure 3
Bolting Liebert EXM UPS to a Liebert EXM TXC
2.
Using supplied hardware, bolt the cabinets together. The bolts may be inserted from either the UPS side or
from the Liebert EXM TXC side, whichever is more convenient.
!
WARNING
Risk of heavy units tipping over while being moved. Can cause property damage, injury and
death.
The Liebert EXM TXC and battery cabinets must be properly prepared and secured for
lifting. Improper lifting may cause the cabinets to fall, causing equipment damage, personal
injury and death.
Vertiv recommends lifting the units with one of the following methods:
• Installing four eyebolts in the factory-fabricated holes, one at each corner of the unit,
attaching cables or similar strapping to the eyebolts and lifting with a suitable
mechanism.
• Placing suitable straps on the Liebert EXM TXC. The straps must go under the unit to
be lifted.
A
DETAIL A
Hex Head Bolt,
M10 x 30mm
Washer Split,
M10
Washer Flat,
M10
Place cabinets so mounting holes are aligned.
A bolt from the adjacent cabinet may be screwed into the threaded top
hole, or a bolt may be inserted through the lower hole and screwed into
the threaded hole in the adjacent cabinet.