4002418-03
569 Ledge Front
INSTALLATION INSTRUCTIONS
CSA approved for use with
Valor Models 530I Heaters ONLY
Notes:
This kit must be installed or serviced
by a qualified installer, service agency or gas
supplier. These instructions are to be
used
in conjunction with the main installation
instructions for the above listed heater
models.
The installation of this kit affects the
framing and method of installing the 530
heater.
530 engine
Touch control
wall switch
Roof
grille
panel
Stand-off
Stand-off
Insulation
Stud bracket
Stud bracket
Convection baffle
Mounting frame
Window frame cover
Cement board
Trim panel—patina, brushed nickel or black
Trim panel
lead-in
assembly
570FPB Finishing Plate
Overview
(530 engine and 570FPB Finishing Plate sold separately)
Installation Sequence
1. Frame the cavity.
2. Install the heater with stud brackets, stand-offs,
insulation, wall switch kit, and cement board.
3. Gas fit and vent heater.
4. Drywall only (no tile, etc.).
5. Assemble and install the mounting frame.
6. Install finishing material (tile, etc.). Finish around or
under 570 Finishing Plate if using it.
7. Assemble and install the trim panel.