Valor 722AP Installation And Owner'S Manual Download Page 11

11

10. GAS SUPPLY CONNECTION

10.1

Fit the gas valve and connector unit to the supply
line.

10.2

Refit the burner unit to the convection box with
three screws.

10.3

Connect the elbow on the gas valve unit to the
burner unit.

10.4

Pressure testing supply line.
Make sure that the gas valve is shut off (control
knob bar at 90° to supply pipe line of flow).
The appliance and its appliance main gas valve must
be disconnected from the gas supply piping system
during any pressure testing of that system at test
pressures in excess of 1/2 psig (3.5kPa).  The
appliance must be isolated from the gas supply
piping system by closing the equipment shut off
valve during any pressure testing of the gas supply
piping system at test pressures equal to or less than
1/2 psig (3.5kPa).

11. CERAMIC WALLS 

INSTALLATION

11.1

Fit the ceramic rear wall inside the “L” brackets
on the back face of the burner compartment. Push
the ceramic wall flat against the back face of the
burner compartment (See figure 15).

11.2

The ceramic side walls can be installed in two
alternative arrangements:
a) With the brick pattern visible - Fit the wall 

stamped “A” at the right side and the wall 
stamped “B” at the left side.

b) With the plain wall surfaces visible - Fit the 

wall stamped “B” at the right side and the wall 
stamped “A” at the left side.

Find out which arrangement the customer requires.
Explain that the customer can not alter the wall
arrangement after the front casting is installed.

Fit the ceramic side walls against the side faces of
the burner compartment. The bottom edges of
the walls should rest on the ledges at the sides of
the fire box and the top of the walls should locate
in the space between the black cross member and
the side walls of the burner compartment (See
figure 16).

12. FRONT & CONTROL

LINKAGE INSTALLATION

12.1

Remove the tape securing the control linking bar to
the casting/surround. Slide the control knob
upwards as far as it will go. This will make sure that
the bottom of the linking bar is higher than the
bottom of the casting/surround when fitting it to
the fireplace

.

12.2

“Adorn front”; Carefully lift the casting. 

Do not lift

it by the control knob. 

Place it against the fireplace

front surface so that the retaining strip at the back of
the casting is above the two upper retaining
brackets at the top of the convection box. Lower the
casting making sure that the rear retaining strip
locates fully over the retaining brackets on the
convection box (See figure 17).

    

  Fig. 15 Ceramic rear wall installation

   Fig. 16 Ceramic side walls installation

        

  Fig. 17 “Adorn” front casting top location

f i r e - p a r t s . c o m

Summary of Contents for 722AP

Page 1: ...ity of this or any other appliance WHAT TO DO IF YOU SMELL GAS Do not try to light any appliance Do not touch any electrical switch Do not use any phone in your building Immediately call your gas supp...

Page 2: ...supply line installation 9 Convection box installation 10 Gas supply connection 11 Ceramic walls installation 11 Front control linkage installation 11 Ceramic coals installation 13 Operation checks 1...

Page 3: ...ity of the appliance after installation e g additional mantle etc make sure that the changes conform to the installation requirements in this manual Never attempt to burn paper or any other material i...

Page 4: ...d in the open position The appliance can be installed in the following constructions 4 1 Solid fuel Non combustible fireplaces As supplied this appliance can be installed as an inset in an existing so...

Page 5: ...E FROM BASE VISAGE FRONT 40 43 OF HEATER B ADORN FRONT 53 with appliance as supplied see page 4 for Valor Cast Suite application 43 with kit 721CRB Fig 2 Clearances to combustible materials in front...

Page 6: ...learance kit enclosure 5 SUPPLY GAS Model 722AN is for use only with natural gas Model 722AP is for use only with propane gas The supply pressure must be between the limits shown in section 3 of this...

Page 7: ...Canopy shield 3 Thread cutting screws for canopy shield 2 Machine screws for front surround fixing or Pack 2 Visage Fire Front contains 1 Fire front surround with sliding control 1 Fire front casting...

Page 8: ...e thermocouple tip see figure 7 If there are no sparks make the following checks a Check condition of battery and that it is correctly fitted b Check spark gap between electrode wire and thermocouple...

Page 9: ...t sulfur compounds 8 3 Unions in gas lines should be of ground joint type 8 4 The gas supply line must be sized and installed to provide a supply of gas sufficient to meet the maximum demand of the ap...

Page 10: ...few inches clear of the fireplace front to allow you to fix the vent connector to the top of the convection box 9 4 Pull the vent connector towards the front of the fireplace and locate the rear slot...

Page 11: ...wall surfaces visible Fit the wall stamped B at the right side and the wall stamped A at the left side Find out which arrangement the customer requires Explain that the customer can not alter the wall...

Page 12: ...y to align the bottom fixing holes with those in the convection box Fix the bottom of the casting surround to the convection box with two screws See figure 19 or 20 12 4 Align the hole near the bottom...

Page 13: ...cess in the burner plaques and touch the ceramic plaques See figure 22 13 2 Place the ceramic front coal in position in front of the base coal Make sure that the side legs of the front coal are fully...

Page 14: ...d the rear multiple coal It has a square hole underneath Place it centrally behind the front multiple coals The square hole must locate in the square peg in the base coal See figure 26 13 6 Place a si...

Page 15: ...justed Lower the casting so that it rests on the floor see figure 29 14 3 Check valve control and slide control for proper operation as described in the lighting instructions section further on in thi...

Page 16: ...ng the guard back Release the springs so that they locate behind the canopy See figure 30 15 2 Visage front Locate the two wires projecting from each side of the guard into the holes in the inner face...

Page 17: ...ire off and allow it to cool before attempting any cleaning Note that the fire will retain heat for some time after it has been turned off Metal parts Clean the metal parts with a slightly damp cloth...

Page 18: ...bel 2 Turn the gas valve control counterclockwise as far as it will go shut 3 Move the control slide knob up to Off 4 Wait five 5 minutes to clear out any gas then smell for gas including near the flo...

Page 19: ...mber It will be helpful if the appliance serial number can also be quoted This is on the chained rating plate visible when the ashpan cover is removed The repair parts are shown in the separate repair...

Page 20: ...20 Manufactured by HEATING BIRMINGHAM ENGLAND Because our policy is one of constant development and improvement details may vary slightly from those given in this publication Valor Ltd fire parts com...

Reviews: