Pressure Relief Valve S3 - Operation and Installation
- 12 -
manual S3-17A-ENG
February 2017
8.
RECEIPT ON SITE
ATENTION! Transport and storage of these devices should be in their original packaging.
RECEIPT ONSITE
When receiving the equipment on site, it should be unpacked to check that they agree with the request and delivery notes. At
least, verification shall be performed:
- Visual,
- Mechanical
After these checks, if it will not be installed immediately, it will keep in dry and protected atmosphere.
Visual Inspection
Check that during transport, unloading and installation, the devices have not been damaged.
Mechanical Verification
Check all moving parts of the apparatus, as well as screws and other elements fulfill their mission.
IMPORTANT!
If is observed abnormality during these guidelines reception, contact urgently VALFONTA to clarify responsibilities
and put the devices in correct status.