background image

 

 

 

VRC Series IOM 

10 

IOM-M2-0316 

Technical Support: (800) 789-8550 

 

Part Number 478603 

Refrigeration Connections 

Both the condenser and ventilator unit are shipped 
with a 20-psi nitrogen holding charge. Relieve 
pressure before cutting or unsweating connection 
stubs.  

Filter drier, sight glass, liquid line solenoid, and 
receiver are factory installed and do not need to be 
field provided. Use ACR refrigeration copper pipe 
only for interconnecting pipe.  

Interconnecting refrigerant lines should be sized 
according to the 

Recommended Line Sizes

 table on 

page 11 unless the application dictates different line 
sizes due to pressure drop or refrigerant velocity. 
Consult the factory before changing line sizes.  

Maximum vertical rise between the ventilator unit 
and condenser is 60ʹ, with 100ʹ maximum, one way, 
total equivalent line length. Equivalent line length is 
equal to the straight pipe line length plus the straight 
pipe equivalent of all the elbows and fittings. Consult 
the factory for larger vertical or line runs. 

Piping should be installed according to accepted 
practices and codes (consult ASHRAE handbook). 
Valent is not responsible for interconnecting piping. 

 Piping/Charging Procedure 

▪ 

Relieve the 20-psi nitrogen holding charge from 
both the ventilator unit and the condenser. 
Relieve pressure from the Schrader port nearest 
each connection. If no pressure is present, check 
for leaks in the system. 

▪ 

Run interconnecting pipe between the systems. 
Discharge line horizontal piping runs should be 
pitched in the direction of flow (1/2″ for every 10ʹ 
of horizontal pipe). Clean and deburr all cut pipe 
before connecting. 

▪ 

Braze connections on each unit under nitrogen 
purge to prevent the formation of copper oxide. 
Wrap a wet cloth around the connection stubs 
near the wall to protect the wall grommets. 

▪ 

If the condenser is over 20ʹ above the ventilator 
unit, an oil drip leg must be field installed at the 
bottom of the first vertical rise in the discharge 
line. If the discharge pipe contains multiple 
vertical rises and horizontal sections, a drip leg 
must be installed at the bottom of any rise over 
10ʹ. Pipe the oil drip legs as shown in the 

Refrigeration Piping Schematic

 on page 12.  

▪ 

Insulate the discharge line for safety (due to high 
pipe temperatures). Insulate the liquid line if it is 
to run through high-temperature areas (over 10°F 
above outside air temperature). 

▪ 

Use nitrogen to pressure check the system to 450 
psi. System should hold pressure for one hour 
with no significant pressure drop. Record pressure 
check (psi) on the 

Condenser Startup Form

 on 

page 16. 

▪ 

Evacuate the system to 500 microns or less. 
Record evacuation microns on the 

Condenser 

Startup Form

 on page 16. 

▪ 

Charge system to the following superheat and 
subcooling with hot gas reheat at 0%. Use the 

Charging Guidelines

 on page 11 for guidance. 

▪ 

Superheat: 10°F–20°F 

▪ 

Subcooling: 10°F–15°F 

Superheat should be measured at the suction line 
port nearest to the compressor. Subcooling 
should be measured at the liquid line port nearest 
to the TXV. Refer to the 

Approximate Charge 

Chart

 on page 11 for base charge and 

approximate refrigerant addition per length of 
interconnecting pipe.  

Record the final charge on the 

Condenser Startup 

Form

 on page 16. Record superheat and 

subcooling values on the ventilator unit start up 
form (VPR IOM PN#472916, Air-Cooled DX 
Startup Form). 

▪ 

Additional oil may need to be added to the system 
based on interconnecting pipe length. On 
compressors with an oil sight glass, the oil level 
should settle between 20% and 80% full in the 
sight glass after 15 minutes of steady-state 
operation.  

Oil should be fairly clear with minimal bubbles 
during steady-state operation. Foggy oil indicates 
the presence of liquid refrigerant and a possible 
over-charge situation. If oil is low in the sight 
glass, add oil to the system though the compressor 
sump port or suction line port. Use POE oil only. 
Record added oil amount on the 

Condenser 

Startup Form

 on page 16. 

▪ 

Use ventilator unit refrigeration start up form to 
complete refrigeration start up (VPR IOM 
PN#472916, Air-Cooled DX Startup Form). 
Record all values requested. 

 

 

Summary of Contents for VRC Series

Page 1: ...MECHANICAL INSTALLATION OPERATION MAINTENANCE VRC Series IOM M2 0316 Part Number 478603...

Page 2: ...learances 4 Lifting Procedure 4 Installation 6 Pad Installation 6 Equipment Support Installation 6 Electrical and Refrigeration Connections 8 Electrical Connections 9 Refrigeration Connections 10 Main...

Page 3: ...before restoring power The Clean Air Act of 1990 bans the intentional venting of refrigerant CFC and HCFC as of July 1 1992 Approved methods of recovery recycling or reclaiming refrigerant must be fol...

Page 4: ...at the top of the unit Unit must be lifted using all lifting lugs on the exterior of the unit Lifting Lug Quantities Casing Lugs 110 4 210 4 310 4 Cables or chains should be at least double the lengt...

Page 5: ...789 8550 Part Number 478603 USE ALL PROVIDED LIFTING LUGS USE SPREADER BAR TO PREVENT DAMAGE TO UNIT CHAIN ANGLE AT POINT OF LUG MUST NEVER EXCEED 20 FROM VERTICAL TEST LIFT UNIT TO CHECK FOR PROPER...

Page 6: ...nd the units have properly undergone the pre startup and startup routines Sound Insulation If the ventilator indoor unit is to be installed above or adjacent to a sound critical area such as an office...

Page 7: ...rt 800 789 8550 Part Number 478603 Minimum Pad Dimensions Unit A B 110 37 75 80 25 210 49 75 110 25 310 66 50 117 00 Dimensions in inches Equipment Support Dimensions Unit A B 110 32 75 75 25 210 44 7...

Page 8: ...ions The following diagrams show piping locations as well as suggested field penetration locations for high voltage and low voltage electrical connections Refer to the Recommended Line Sizes table on...

Page 9: ...need to be connected between the ventilator unit and condenser Refer to the table below for required field wiring All control wiring is low voltage 24 volts or less Fan modulation signal wiring 0 10...

Page 10: ...ge line If the discharge pipe contains multiple vertical rises and horizontal sections a drip leg must be installed at the bottom of any rise over 10 Pipe the oil drip legs as shown in the Refrigerati...

Page 11: ...r 2 turns Low superheat and normal subcooling Under restricted Tighten TXV adjustment screw by 1 or 2 turns High superheat and high subcooling Over restricted Loosen TXV adjustment screw by 1 or 2 tur...

Page 12: ...A oz Circuit B oz 110 5 10 7 12 5 1 0 8 15 6 17 9 1 1 10 20 2 N A 1 8 210 10 9 8 8 0 13 6 11 8 1 0 1 0 13 11 0 12 9 13 6 15 8 1 0 1 1 16 16 4 13 5 18 1 15 0 1 1 1 1 18 16 2 17 0 20 4 20 9 1 1 1 8 20 2...

Page 13: ...ressure water can be used to clean coils Spray in the direction opposite the airflow to push dirt out the front of the coil Test the spray pressure on a small area on a corner of the coil to see how w...

Page 14: ...rect if possible Line wiring to motor too small Install larger wiring 60 Hz motor connected to 50 Hz line supply Replace unit with 50 Hz motor Motor wired for wrong voltage Check wiring Motor takes to...

Page 15: ...ed DX Startup Form to Valent via US Mail Valent Startup Forms 60 28th Avenue North Minneapolis MN 55411 E mail Subject Valent Startup Forms OAPservices unisoncomfort com Fax ATTN Valent Startup Forms...

Page 16: ...System has been pressure checked to 450psi with nitrogen for 1 hr System has been evacuated to less than 500 microns before charging Condenser Startup Form Prior to starting the unit ensure that all a...

Page 17: ...Certified Technician Startup services include verifying proper operation of the unit including proper refrigerant charge and repair of minor refrigerant leaks outside the coil At the completion of st...

Page 18: ...ties begin at start up or 6 months after the date of shipment from the Unison factory whichever occurs first The ship date for the units noted above is Please refer to the Unison Comfort Technologies...

Page 19: ...eration 10 Cooling coil maintenance 10 13 Curb Dimensions 7 Installation 6 Design requests 3 Ductwork dimensions 7 Installation Curb 6 Pad 6 Lifting instructions 4 Line sizes 11 Model numbers 3 Motor...

Page 20: ...March 2016 Valent is a business of Unison Comfort Technologies For service inquiries please contact Unison Comfort Technologies Technical Service 800 789 8550 OAPservices unisoncomfort com...

Reviews: