background image

ecoTEC exclusive installation and maintenance instructions / 0020017768_02

16

5.9 Condensate 

discharge

7

d

Soakaway

c

6

5

Gulley

a

Internal
stackpipe

3

4

3

b

Internal
discharge system

1

2

Fig. 5.11 Condensate discharge

The ecoTEC exclusive units are equipped with a normal 
water condensate collector where the condensate is 
continuously diverted into the drain pipe. 
•  Connect the condensate drain (

1

) of the boiler to a 

condensate drain pipe (

2

) which has a minimum inter-

nal diameter of 19 mm (22 mm outside diameter for all 
external pipes) and which is made from an acid-resist-
ant material (e.g. plastic overflow pipe).

h

 Note!

The drain pipe connected to the condensate 
drain of the boiler must have a constant gradi-
ent (45 mm per metre) and should be installed 
and terminate within the building to prevent 
the possibility of freezing up.

The condensate drain pipe should terminate in a suita-
ble location, e.g.:
a) The drain pipe should preferably terminate in the floor 

of the house in the ventilation duct (at least 450 mm 
above the duct base). There must be a siphon (

3

) fitted 

in the line (mounted in the boiler) producing a connec-
tion head of at least 75 mm of water. A ventilation 
valve (4) must be fitted in the drain pipe in front o

f

 the 

siphon. The connection to the ducting should not allow 
overflow into another drain pipe or allow overflow from 
another drain pipe into the condensate drain pipe. This 
can be achieved by keeping a gap between the pipe 
branches of at least 110 mm, with a duct diameter of 
100 mm, and 250 mm with a duct diameter of 150 mm. 

b) Connection into the domestic waste water drain pipe 

(e.g. a sink or washing machine) with an external ter-
mination. The condensate drain pipe should have a 
minimum diameter of 22 mm, without length restric-
tion, and also be fitted with a siphon (

3

) having a con-

nection head of 75 mm (fitted within the boiler al-
ready). The connection should be made after the drain 
siphon if possible. If the installation is only possible in 
front of the siphon, there must be a ventilation valve 
between the two siphons. This is normally provided in 
a drain.

c) Draining into a gully (

5

) under the grid (

6

) and above 

the water level. The external piping should be kept as 
short as possible to minimise the frost risk, and should 
be no longer than 3 m.

d)To the condensate absorption point (drainage ditch)

 (7

). 

The external pipe should have a maximum length of 3 m.

Further information can be obtained from "BS 6798 
Specification for installation of gas–fired boilers of rated 
input not exceeding 70 kW net". The condense trap (1) 
must be filled with water as described in the relevant 
section before the boiler is commissioned.

5.10 Electrical 

connection

d

  Danger!

The electrical installation may only be under-
taken by an authorised engineer.
Risk of fatal electric shock from touching live 
connections. Always disconnect the power sup-
ply first by pulling the plug out of the wall 
socket. Only after this can the installation be 
undertaken. Continuous voltage is present on 
the mains connection terminals L and N, even if 
the main switch is turned off!

5.10.1 Mains 

connection

The appliance is fitted with a 1.0 m long connection 
cable with mains plug. The three-pole mains plug is fit-
ted with a 3.0 A fuse. The connection cable is wired into 
the appliance in the factory.
Connection to the mains supply shall be made via the 
fused 3 pin plug to an unswitched shuttered socket, 
complying to the requirements of BS 1363.

5.10.2  Connection of controllers, accessories and 

external installation components

The following controllers, accessories and installation 
components can be connected to the ecoTEC exclusive 
(see Table 5.2).
The installation should be carried out in accordance with the 
individual instruction manual. The required connections to 
the electronic system of the boiler (e.g. for external control-
lers, external sensors etc.) should be undertaken as follows:
•  Remove the front cover of the device, and lower the 

electronic box forward.

•  Unclip the rear cover of the electronic box and hinge 

the cover upwards.

•  Insert the connection lines of the components to be 

connected through the cable openings (

1

) on the left 

hand side of the underside of the appliance.

5 Installation

Summary of Contents for ecoTEC exclusive SERIES

Page 1: ...For the installer Installation and maintenance instructions ecoTEC exclusive Gas wall boilers with condensing appliance technology ecoTEC exclusive 832 ecoTEC exclusive 838 GB...

Page 2: ...1 4 Filling the condense trap 22 6 2 Checking the gas setting 22 6 2 1 Checking the connection pressure gas inlet working pressure 22 6 2 2 Checking CO2 content and setting if necessary setting the a...

Page 3: ...the operator of the in stallation in order for him or her to store it so that it is available whenever it is required 1 2 Safety instructions and symbols Please observe the safety instructions in thi...

Page 4: ...N 483 EN 625 EN 677 EN 50165 EN 55014 EN 60335 1 EN 60529 EN 61000 3 2 EN 61000 3 3 hVaillant Ltd supports the Benchmark Initiative You will find the Benchmark Logbook on the last page of this instruc...

Page 5: ...n problems can be caused if the tank is not bled properly In such cases first contact the person in charge of filling the tank Affix tank sticker Affix the enclosed tank sticker propane quality on the...

Page 6: ...e current Version of I S 813 Domestic Gas Instal lations and the current Building Regulations The current ETCI Regulations for the installa tion of electrical equipment must also be ob served a Cautio...

Page 7: ...rriage of carton from point of delivery to point of installation first or higher floor cellar Recommend 2 person lift or 1 person with use of sack truck If 1 person is performing lift straddle the loa...

Page 8: ...nd ensure good grip when handling appliance Positioning of Appliance for Final Installation within compartment etc restricting installation If appliance weight is over 25 kg always use 2 persons to mo...

Page 9: ...ing and dimensions for connection 70 190 480 800 2 25 450 7 20 100 100 20 5 3 7 20 20 R 1 2 180 4 6 Fig 4 2 Dimensions for connection mm Key to Fig 4 2 1 Flue connection 2 Mounting bracket 3 Heating r...

Page 10: ...stallation in timber framed and light steel framed buildings Please note the following instructions before choosing where to install the heater a Caution Do not install the appliance in rooms prone to...

Page 11: ...together so that the front cladding releases Pull the housing forwards at the lower edge and re move the front cladding upwards 5 Installation d Danger The Vaillant ecoTEC exclusive may only be in sta...

Page 12: ...for natural gas and 37 mbar for propane gas The gas pipe should first be cleaned by blowing out with compressed air This prevents damage to the appliance Connect the compression gas service cock and...

Page 13: ...ed with the appliance for top connection of the flow and return pipework within the casing 5 5 Pressure Relief Valve Fig 5 4 Fitting the pressure relief valve The pressure relief valve and filling loo...

Page 14: ...ity during installation 1435 10 550 880 40 Fig 5 6 Item No 303900 5 6 2 Optional 125 mm flue pipe A concentric flue pipe having an outside diameter of 125 mm is available which can be extended to a le...

Page 15: ...iler Installation which recommends 2 5 m from wall fence or boundary Where a plume diverter terminal is used this is measured in the direction of the flow of products BS 5440 1 We recommend that the t...

Page 16: ...re must be a ventilation valve between the two siphons This is normally provided in a drain c Draining into a gully 5 under the grid 6 and above the water level The external piping should be kept as s...

Page 17: ...7 8 9 Danger of destroying the electronics hNote There is no provision set in the factory for connection of an installation thermostat for underfloor heating hNote Make sure that the connection cables...

Page 18: ...been made The cover is secured with two clips Controller Item no Connection VRT 400 single circuit weather compensator 307 409 Installation in electronics box plug and play VRT 240 room thermostat 307...

Page 19: ...Room thermostat 230 V 50 Hz Remove bridge when connecting Heating pump Mains connection 230 V 50 Hz Igniter Caution Do not connect mains voltage Danger of damage to the electronics Diagnosis via eBUS...

Page 20: ...NTC X 20 5 red X 20 7 black X 20 7 black X 20 8 blue X 2 12 green X 2 11 red X 2 9 black Pump X 20 18 red 24 VDC X 20 9 blue Earth X 20 16 blue Earth X 20 4 grey PWM X 20 3 black Hall signal X 20 17...

Page 21: ...e by pushing the minus button Turn the rotary knobs 1 and 4 to the left hand stop and switch the unit on using the main switch 3 h Note Use the test programme P 6 for filling the heating system The pr...

Page 22: ...ion out of the heating system before the boiler is started up Close the 1 2 KFE drain cocks Re fill the heating system with water as described in Section 6 1 1 Check that the over pressure valve in th...

Page 23: ...the sealing screw is not leaking Put the front cover back on and turn on the device If the connection pressure is not within the permissible range and you cannot resolve the problem inform the gas su...

Page 24: ...m a function check before commissioning the ap pliance and handing over to the user Commission the appliance in accordance with the in structions in the relevant operating manual Check the gas infeed...

Page 25: ...m cover upwards until the spring retaining clips engage at the side of the appliance It may be necessary to adapt the bot tom cover by removing the easy break sections 6 4 Handing over the appliance t...

Page 26: ...ion see Chapter 8 Using the following description you can select the rele vant parameters Press the i and buttons simultaneously The display shows d 0 Scroll to the desired diagnosis number with the o...

Page 27: ...You can enter your settings in the end column after setting the appliance specific parameters hNote The diagnosis points d 17 d 71 and d 84 are lo cated in the 2nd diagnosis level see Chapter 9 1 2 7...

Page 28: ...d thermal properties of the heating installa tion In the factory the burner anti cycle time is set to a value of 20 minutes It can be varied under diagnosis point d 02 within the range 2 minutes to 60...

Page 29: ...1 Volumeflow l h Lift mbar Fig 7 2 Characteristic pump line for ecoTEC exclusive 832 and 838 Key to Fig 7 2 1 at 27 kW 2 at 30 kW 7 3 Adjusting the bypass valve The appliances have a bypass valve The...

Page 30: ...maintenance cocks if fitted in the heating flow and return and the cold water inlet valve on the inlet combination Remove the front cover from the device Always perform the following steps after perfo...

Page 31: ...2 3 or 5 above Clean the primary heat exchanger Fit a new burner door seal kit spareparts no 0020026401 observe the assembly instructions enclosed with the seal kit Refit the burner module and tighten...

Page 32: ...ion und grounding lines off the ignition electrode 4 Only ecoTEC exclusive 832 Pull the cable plug off the fan motor and the cable off the gas fitting Only ecoTEC exclusive 838 Open the mains coupling...

Page 33: ...3 2 1 6 Fig 8 5 Installing compact thermal module Place the entire compact thermal module 5 onto the integral condensation heat exchanger Tighten the five nuts 2 across the diagonal until the burner d...

Page 34: ...pliance Release the nut 4 on the secondary heat exchanger Release the clamp 1 on the preference changeover valve Release the clamps 2 and 3 on the secondary heat exchanger Remove the secondary heat ex...

Page 35: ...8 1 Checking the connection pressure gas inlet working pressure To check the connection pressure proceed as described in Chapter 6 1 2 8 8 2 Checking CO2 content and adjusting if necessary To check t...

Page 36: ...water Storage tank charging heat retention mode Page 20 Water pump flow S 21 Fan start S 23 Ignition S 24 Burner mode S 25 Fan and water pump return water S 26 Fan return flow S 27 Water pump return w...

Page 37: ...y flashes Save the new value by holding down the i button for approx 5 seconds until the display no longer blinks You can end the diagnosis mode as follows Press the i and buttons simultaneously or Do...

Page 38: ...ostat 24V DC on terminal 3 and 4 0 Room thermostat open no heat request 1 Room thermostat closed heat request d 22 Hot water demand 1 on 0 off d 23 Summer mode heating on off 1 heating on 0 heating of...

Page 39: ...ssful ignitions in the last attempt d 64 Average ignition time in seconds d 65 maximum ignition time in seconds d 68 Unsuccessful ignitions at the first attempt number d 69 Unsuccessful ignitions at t...

Page 40: ...25 Interruption in cable harness Cable harness faulty F 27 External light Gas solenoid valve defective flame detector defective F 28 Appliance does not start Attempts to ignite during start failed Fa...

Page 41: ...is turned on and the button is pressed for 5 seconds simultaneously The display shows P 0 Press the key to start counting the test pro gramme number upwards Press the i to operate the appliance now an...

Page 42: ...Use only new gaskets and O rings After completing the work check for gas leaks and perform a function check see Chapter 6 10 2 Replacing burner d Danger Before replacing the component comply with the...

Page 43: ...afety instructions in Section 10 1 Disconnect the appliance from the mains as described in Chapter 10 1 and close the gas cock in the gas supply pipe Close the maintenance cocks if fitted in the heati...

Page 44: ...ge F 70 In the second diagnosis level under the diagnosis point d 93 enter the number of appliance variant according to Table 10 1 see Chapter 9 1 2 The electronics is now set to the appliance type an...

Page 45: ...r Required connection pressure 0 35 0 35 bar Hot water discharge temperature range 35 65 35 65 C General Gas connection 15 15 mm Heating connection 22 22 mm Hot and cold water connection 15 15 mm Exha...

Page 46: ......

Page 47: ......

Page 48: ...0020017768_02_GB 03 2008...

Reviews: