14
VADA FLOW BOSS
SUBMERSIBLE PUMP
VFB-S75
INSTALLATION MANUAL
Note:
When lifting or raising in and out of
position, please use nylon rope supplied.
Do not lift via the power cable.
4. Check the set up so far. The surface
the pump sits on should be hard and there
should be enough clearance between
the base of the tank and suction inlet
(approx 50–100mm). This clearance helps
prevent sediment and debris from entering
the pump.
PART 2: DISCHARGE
SET UP
It’s time to set up the discharge
pipework.
Note:
The length and diameter of the
discharge hoses/pipes will affect the pressure
and flow rate at which your pump operates.
Pressure ratings of all components must
exceed the maximum pressure of the pump
by an appropriate safety factor.
1. Create space for your discharge pipe
work at the top of the tank. Connect the
discharge pipe to outlet port of the pump.
2. Lower the pump and discharge pipe work
into the tank.
INSTALLATION