Each VACON
®
NXP System Drive delivery is project specific. The following installation sequence is
a general description of the process of connecting the cabinet sections and installing the system
drive.
As each installation is project specific, the instructions and illustrations in the following chapters
are general examples. More detailed instructions, such as layout drawings, dimensions and wiring
diagrams, are included in the project delivery.
1
Before starting the installation, read the safety instructions in Chapter 2 carefully.
2
Make sure that the ambient conditions at the installation site are according to the
specifications. See the specifications in Chapter 6.3.
Remove the package covering from the product only at the installation site and in the
specified ambient conditions.
3
Before moving the cabinets to the installation site, make sure that the space is
properly prepared for the installation. See Chapter 4.2.
4
Move the cabinets to the installation site. See the instructions in Chapter 1.8.
5
Make sure that there is enough free space around the cabinets. See Chapter 4.2.1.
6
Lift the first cabinet section into the desired installation location. See Chapter 4.3.
7
Fix the first cabinet section to the floor or wall. See Chapter 4.3.
8
Lift the second cabinet section next to the first section, in a position from which it can
be pushed into place.
9
Before pushing the cabinets together, loosen the nuts and bolts on the ends of the
busbars to be connected. See Chapter 4.4.
10
Push the cabinets together, make sure that the busbars come together properly.
11
Connect the busbars by tightening the nuts and bolts on the busbars. See Chapter 4.4.
12
Mount the cabinet frames to each other. See Chapter 4.5.
13
Mount the second section to the floor or wall.
14
Install the rest of the sections following the same procedure.
15
Once all the cabinets are connected, remove the lifting beams from the top of the
cabinets, so that they do not block the air flow. After the beams are removed, mount
the bolts back on the cabinet roof.
16
Do the cabling between cabinets (auxiliary low-voltage connections, fiber
connections, etc.). See the project specific wiring diagrams, which are included in the
delivery.
17
Connect the motor and mains cables to the system drive. Pay attention to grounding
of the cables. See Chapter 4.6.