4.2 Commissioning
4.2.1 Commissioning steps:
1. Read safety instructions on page 1
2. Secure the grounding and check that cables comply with
requirements
3. Check quality and quantity of cooling air
4. Check that the possible start/stop switch is in STOP posi-
tion
5. Connect the drive to mains
6. This step is not valid for API RS-485
7. Perform test run without motor, see the User Manual at
www.vacon.com
8. Run no-load tests without motor being connected to the
process
9. Connect the motor to the process and perform test run
once again
10. Vacon 10 rs-485 is now ready for use
Table 1: Commissioning steps
Green
Green
Red
Red LED on:
Vacon 10 is not ready
(e.g. supply voltage too low)
Red LED is blinking:
there is an active fault
(See chapter 6)