POSITIONING THE FOUNDATION BOX AND THE LEVER CONTROL 
AND BLOCKING SYSTEM

250 mm

600 mm

450 mm

450 mm

600

 mm

450 mm

3 mm

3 m

m

> 67 mm

1. 

Depending on the dimensions, dig a suitably sized foundation 
ditch (it is recommended to provide adequate drainage in order 
to avoid water pooling).

2.

  Place the foundation box inside the trench, with the support 

pivot aligned with the hinge axis.

3.

  Install a conduit for the electrical cables, and another for 

drainage.

4.

  Embed the foundation box in concrete, ensuring it is level and 

plumb.

m

 WARNING:  ensure that the concrete used is properly 

cured prior to proceeding with the following steps.

5.

  Insert the control rod 

A

 over the foundation box supporting 

pivot 

B

.

6.

  Insert the ball 

E

 into the special hole after having greased it 

7.

  Fix with a strong welding the wing of the gate on the release 

lever 

C

, then put everything on the driving bracket 

A

 in 

correspondence of the hole

8.

  Grease the mechanism using the appropriate grease nipple 

D

 

 

 

 

Summary of Contents for Vulcan

Page 1: ...Value moves the world ZIS142 IL 245 EDIZ 08 05 2017 VULCAN GB IRREVERSIBLE ELECTROMECHANICAL ACTUATOR UNDERGROUND INSTALLATION FOR LEAF GATES...

Page 2: ...147 5 200 224 343 37 5...

Page 3: ...carefully before installing and programming your control unit This instruction manual is only for qualified technicians who specialize in installations and automations The contents of this instruction...

Page 4: ...00 2 5 x 550 3 x 400 3 5 x 350 2 x 800 2 5 x 550 3 x 400 3 5 x 350 2 x 800 2 5 x 550 3 x 400 3 5 x 350 Power supply V Hz 24 120 60 230 50 230 50 Idling current A 1 3 1 5 1 5 Maximum current absorption...

Page 5: ...oundation box see paragraph about Installation of the stop limit switches INSTALLATION LAYOUT 1 1 2 4 3 C 5 D A B LENGTH OF THE CABLE 10 metres from 10 to 20 metres from 20 to 30 metres Power supply 2...

Page 6: ...Install a conduit for the electrical cables and another for drainage 4 Embed the foundation box in concrete ensuring it is level and plumb mWARNING ensure that the concrete used is properly cured pri...

Page 7: ...attach the limit switch screw as shown in the figure 2 Place the gate in the maximum open position and then attach the limit switch nut as shown in the figure and tighten the screw 3 Mount the motor c...

Page 8: ...TION extensions of the cables must be made only with a 4x0 22 shielded cable with polyethylene sheath mATTENTION connect the shielding braith sheath to the common accessories Check that the ground of...

Page 9: ......

Reviews: