To open the cold water/primary flow strainer, use internal
hexagon (

6 mm

).

The strainer collects dirt and its filter can be removed for inspection
and cleaning.

1.5 Filling, flushing and venting

The filling and draining valve (A) on the primary heating can be used
for filling and flushing of the heating system.

Ventilation is done by turning the ventilation screws (B).

1.6 Tightness testing

Warning!

Leaking connections can cause personal injury and
property damages.

1.7 Hydraulic installation

Warning!

Risk of injury due to improper installation!

Ensure that the hydraulic connections are made in a
correct way. Leaking connections can cause personal
injury.

Note

Use the hydraulic diagram in the end of the document as
an installation guide.

Do not reduce the specified pipe cross-sections. The
connections for optional components (e.g. meters) are capped
with black plastic adaptors in the device.

Replace the plastic fittings with stainless steel 1.4401 pipes if no
optional components should be connected. These can be
obtained from the supplier.

Ensure to connect the heating supply and return as well as the
hot and cold water correctly.

Install a filling and draining valve on site at a suitable central
point to fill the central heating system.

1.8 Electrical installation

Warning!

Risk of electric shock if touching the components! The
unit operates with a 230 V AC voltage.

Warning!

Required electrical connections and installations,
commissioning and maintenance must only be performed
by an authorised person in accordance with local
standards and regulations.

Note

Use the wiring diagrams in the end of the document as
installation guides.

1.9 Visual inspection

Caution!

Improper commissioning can lead to property damage.

Note

If an installation error is found during visual inspection,
temporarily stop commissioning and rectify the error.

Complete commissioning by following these steps:

1.

Make a complete check up of the installation prior to
commissioning:
1.1.

Make sure that the hydraulics are connected correctly

1.2.

Check that any dirt accumulated during installation and/or
dust on the unit has been removed properly. Check
strainers and, if necessary, flush/clean them.

1.3.

Check the tightness of all seals on pipe - and device
connections and tighten them if necessary. When
tightening connections, always lock the opposite side

1.4.

Optional: Check that all electrical connections have been
made correctly, including polarity of the mains connection
and that grounding is assured.

2.

Check that the installation is filled/flushed and vented.

 |  

Combi Port Base

  |  

Quick guide

EN

Summary of Contents for KaMo Combi Port Base

Page 1: ...Combi Port Base EN Quick guide CZ Stru n pr vodce DE Quick guide SK Stru n n vod INT CD0000402 PDF w w w...

Page 2: ...ents EN 3 1 Installation and commissioning 3 CZ 5 1 Mont a uveden do provozu 5 DE 7 1 Installation und Inbetriebnahme 7 SK 9 1 In tal cia a uvedenie do prev dzky 9 INT 11 2 Combi Port Base Quick guide...

Page 3: ...y damages Before installing the heat interface unit ensure that the primary pipes are laid in the building site the primary pipe installation is flushed and checked for leaks the power and ground cabl...

Page 4: ...suitable central point to fill the central heating system 1 8 Electrical installation Warning Risk of electric shock if touching the components The unit operates with a 230 V AC voltage Warning Requir...

Page 5: ...dy na majetku P ed instalac bytov stanice se ujist te e Prim rn potrub je na stavb polo eno Potrub na m st instalace je vypl chnut a zkontrolovan z hlediska net snost M sto instalace je vybaveno nap j...

Page 6: ...ve vhodn m centr ln m bod plnic a vypou t c ventil aby bylo mo n syst m st edn ho topen plnit 1 8 Elektrick instalace V straha Nebezpe razu elektrick m proudem p i kontaktu se sou stmi Za zen vy aduj...

Page 7: ...sicherzustellen dass sie vor dem Anschluss fest angezogen sind Vor der Installation der Wohnungsstation sicher gehen dass die prim rseitigen Rohre auf der Baustelle verlegt sind die prim rseitigen Le...

Page 8: ...ralen Stelle um das Zentralheizungssystem zu f llen 1 8 Elektroinstallation Warnung Stromschlaggefahr beim Ber hren der Bauteile Das Ger t wird mit 230 V Wechselspannung betrieben Warnung Die erforder...

Page 9: ...jetku Pred in tal ciou bytovej stanice tepla sa uistite e Prim rne potrubia s namontovan na stavbe Prim rne potrubia na stavbe s prepl chnut a skontrolovan vo i netesnostiam V mieste in tal cie s nap...

Page 10: ...vykurovacieho syst mu in talujte plniaci a vyp ac ventil aby bolo mo n syst m napusti 1 8 Elektroin tal cia V straha Nebezpe enstvo razu elektrick m pr dom pri dot kan sa komponentov Jednotka pracuje...

Page 11: ...65 CD0000310 b l1 w1 l w h1 h l l1 w w1 h h1 b 555 5 82 75 618 600 105 35 65 l1 w w2 w3 w1 l h1 h ZD0000026 l l1 w w1 h h1 b b1 795 750 1240 1190 110 135 1189 5 22 35 l1 w w2 w3 w1 l h1 h ZD0000025 l...

Page 12: ...w1 h h1 h2 h3 h4 l1 l l3 b1 w1 w2 w3 CD0000318 l l1 w w1 h h1 b b1 795 750 1440 1190 110 135 1189 5 22 85 12 Combi Port Base Quick guide...

Page 13: ...SI0000365 1 2 3 4 1 2 SI0000366 5 6 7 SI0000367 1 3 CD0000306 Combi Port Base Quick guide 13...

Page 14: ...SI0000368 1 4 A 1 4 B A 1 6 2 h P 1 5 CW HM 14 Combi Port Base Quick guide...

Page 15: ...1 7 SI0000369 Combi Port Base Combi Port Base TWB Combi Port Base Quick guide 15...

Page 16: ...6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 3 7 5 8 9 7 10 11 6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1 8 12 6 5 4 3 2 1 6 4 30 30 30 30 30 30 30 30 BN BU 2 1 230 V 50 Hz SI0000370 BN BU BN...

Page 17: ...Combi Port Base Quick guide 17...

Page 18: ...18 Combi Port Base Quick guide...

Page 19: ...Combi Port Base Quick guide 19...

Page 20: ...o make changes without prior notification to the specification of incorporated components in line with its policy of continuous improvement and development www uponor com 1103132 v1_06_2020 INT Produc...

Reviews: