12 l Uponor Combi Port PRO XU l Installation manual
3
Installation
3.1
Mounting back plate or rail
1
Mark for drilling.
Note
Pay attention to horizontal alignment!
2
Drill holes.
3
6FUHZEDFNSODWHZLWKHQFORVHG¿[LQJPDWHULDOWRWKHZDOO
Note
The corresponding primary supply lines must be installed
at the ball valves ¾”:
When it is required to connect pipes variable on top,
down or both top&down, then the back plate to be used
For pipe connections all on top, the rail to be mounted.
In this mounting instruction the case A will be shown, as this is the
more advanced one.
3.2
Mounting connection pipes for UFH
manifold
1
Screw down 2 ball valves (right site, heating connections)
and close the 2 pipes with caps ¾”.
2
Fix the ball valves down to the connecting pipes.
3
Fix the connecting pipes on the back plate.
A Variable connections:
top, down or top & down
B All pipe connections
on top.