Installation
ThrOugh ThE wALL iNSTALLATiON
(RECOMMENDED INSTALLATION)
To vent the unit through the wall, connect the pipe adapter
to the exhaust motor adapter. If the exhaust adapter is at
least 18-inches above ground level, a straight section of
pellet vent pipe can be used through the wall.
Your
King
dealer should be able to provide you with a kit
that will handle most of this installation, which will
include
a wall thimble that will allow the proper clearance through
a combustible wall. Once outside the structure, a 3-inch
clearance should be maintained from the outside wall and a
clean out tee should be placed on the pipe with a 90-degree
turn away from the house. At this point, a 3-foot (minimum)
section of pipe should be added with a horizontal cap, which
would complete the installation (see FIGURE 7).
A support bracket should be placed just below the
termination cap or one every 4-feet to make the system
more stable. If you live in an area that has heavy snowfall,
it is recommended that the installation be taller than 3-feet
to get above the snowdrift line. This same installation
can be used if your stove is below ground level by simply
adding the clean-out section and vertical pipe inside until
ground level is reached. With this installation you have to
be aware of the snowdrift line, dead grass, and leaves. We
recommend a 3-foot minimum vertical rise on the inside or
outside of the house.
The “through the wall” installation is the least expensive and simplest installation. Never terminate the end vent under a
deck, in an alcove, under a window, or between two windows. We recommend Simpson Dura-Vent
®
or Metal-Fab
®
kits.
ThrOugh ThE rOOF/CEiLiNg iNSTALLATiON
When venting the stove through the ceiling, the pipe is connected the same as through the wall, except the clean-out
tee is always on the inside of the house, and a 3-inch adapter is added before the clean-out tee.
You must use the proper ceiling support flanges and roof flashing (supplied by the pipe manufacturer; follow the pipe
manufacturer’s directions). It is important to note that if your vertical run of pipe is more than 15-feet, the pellet vent pipe
size should be increased to 4-inches in diameter.
Do not exceed more than 4-feet of pipe on a horizontal run and use as few elbows as possible. If an offset is required,
it is better to install 45-degree elbows rather than 90-degree elbows.
FigurE 7
TYPICAL THROUGH THE WALL INSTALLATION