INSTALLING PERMANENT METER UP-2210R/P
The installation process involves fitting the measuring device in an existing equipment cabinet or
similar meter at the selected installation site. This includes the connection to existing instrument
transformers and the chosen communication equipment. The connection to the instrument
transformers must
only
be made by qualified electrical installers or equivalent personnel to prevent
injury during installation. We recommend making the connections to the measure core and only in
exceptional cases directly to the relay cores.
4.1
Location and fitting
UP-2210R is designed to be installed in standard 19” rack. UP-2210P is designed to be installed in a
panel.
Figure 5