Unimi-1baseHPC dimensions: 
 
 
 

 

Length (at the base) 

1200 mm  

 

Depth (at the base) 

1200 mm 

 

Length (at the top) 

720 mm 

 

Depth (at the top) 

590 mm 

 

Height   

 

775mm 

 

Weight   

 

1270 kg 

 
 
 
 
 
 

 

  

 

 

 

 

 

 

 

        

                

Measurements top view 

 
Installation procedure: 
 
 

1.  To off-load the Unimi-1baseHPC either use fork-lift for the EUR pallet on which the foundation is 

loaded  or  use  a  lift  sling  attached  to  the  two  lifting  anchors  positioned  at  either  long  side  of  the 
foundation. 
 

2.  The  cavity  where  the  Unimi-1baseHPC  shall  be  installed  should  be  large  and  deep  enough  so 

that  the  underlying  ground  can  be  prepared  in  such  a  way  that  water  will  drain  away  from 
underneath the station. Ideally, draining layer of gravel should penetrate below ground frost level 
of where the installation site is situated. The cavity should allow work with ground stomp machine 
both  below  and  at  the  sides  of  the  foundation.  The  local  conditions  and  machinery  used  by  the 
installer will be the determining factor for the size of the cavity. As a minimum we recommend 300 
mm wider on each side than the foot of the base (1800x1800 mm).  
 

3.  The intention is to have the top of the Unimi-1baseHPC foundation flush with surrounding ground 

level (excluding the adaptor element that will add 10 mm at the top after installation). Depending 
on  local  conditions  such  as  water  drainage  it  may  be  required  that  the  foundation  top  protrudes 
from  final  ground  surface.  This  should  not  exceed  100  mm  if  integrated  Unimi-1baseHPC  crash 
protections will be installed on the foundation. 
 

4.  If  possible,  with  regards  to  the  above,  we  recommend  that  200  mm  in  each  direction  from  the 

foundation top shall be flush. Although not a necessity, this will make future swap of adaptors to 
other station brands easier as those adaptors may have to be off set from foundation center 

 
5.  When  installing  the  Unimi-1baseHPC  pay  close  attention  to  the  orientation  of  the  foundation  so 

that it is aligned with the station design and intended facing towards charging vehicles and users 

 

6.  The  Unimi-1baseHPC  has  1x112  mm  conduit  inlet  and  1x51  mm  conduit  inlet  in  each  direction. 

Unused conduit openings will be covered with plastic lids  
 

a.  From June 2020 there will be a pan European version of Unimi-1baseHPC that will have 

2x142 mm conduit openings on one of the short sides and on one of the long sides. This 
to better align with the standards used in different regions of Europe  
 

7.  If necessary, plastic attachment adaptors may be used between the foundation conduit inlet holes 

and the plastic conduits. Installation expansion foam may also be used. (None of these supplied 