PART III: OPERATION
24
Integrated proving system (burners equipped with LME7x, LMV, LDU)
Adjustments - brief description
The air and fuel rates adjustments must be performed at the maximum ouptput first (“high flame”): see the LMV5.. related manual..
Check that the combustion parameters are in the suggested limits.
Check the flow rate measuring it on the counter or, if it was not possible, verifying the combustion head pressure by means of a dif-
ferential pressure gauge, as described on par. “Measuring the gas pressure in the combustion head”.
Then, adjust the combustion values by setting the “gas/air” ratio” curvepoints (see the LMV5.. related manual).
Set, now, the low flame output, in order to avoid the low flame output increasing too much or that the flues temperature gets too low
to cause condensation in the chimney.
Adjusting procedure
Go on adjusting the burner.
Users can set only the LMV parameters that can be accessed without password: (see “Adjusting the temperature set-point”).
The Siemens AZL User Interface allows programming the Siemens LMV system and monitoring the system data.
The user interface is made of:
1. display: it showes menus and parameters
2. ESC key (previous level): it goes back to the prevoius level menu or exits the programming mode without changing data.
3. ENTER key (next level): it confirms the data changing and jumps to the next menu/parameter.
4. SELECT keys: they select a menu item and change the parameter values.
As far as the settings, see the LMV5 related manual.
By following the “air/gas ratio” curvepoints setting procedure on the LMV5.. manual, adjusting the air and gas flow rates: check, conti-
nuosly, the flue gas analisys, as to avoid combustion with little air; dose the air according to the gas flow rate change following the steps
PS
EV1
EV2
/
EV2
EV1
PGCP
This paragraph describes the integrated proving system operation sequence:
At the beginning both the valves (EV1 and EV2) must be closed.
Test space evacuating: EV2 valve (burner side) opens and keep this position for a preset time
(td4), in order the bring the test space to ambient pressure.Test atmospheric pressure: EV2 clo-
ses and keep this position for a preset time (test time td1). The pressure switch PGCP has not to
detect a rise of pressure.
Test space filling: EV1 opens and keep this position for a preset time (td3), in order to fill the test
space.
Test gas pressure: EV1 closes and keep this position for a preset time (td2). The pressure switch
PGCP has not to detect a pressure drop down.
If all of the test phases are passed the proving system test is successful, if not a burner lockout
happens.
On LMV5x and LMV2x/3x and LME73 (except LME73.831BC), the valve proving can be parameteri-
zed to take place on startup, shutdown, or both. On LME73.831BC the valve proving is parameteri-
zed to take place on startup only.
1
2
3
4
Summary of Contents for RX1025.1
Page 41: ......
Page 42: ......
Page 43: ......
Page 45: ...User manual Siemens LMV 5x M12914CA Rev 0 03 2008...
Page 46: ......
Page 57: ......
Page 58: ......
Page 59: ......
Page 62: ...Annex1 Example for motor cable...
Page 63: ......
Page 64: ...Annex 2 Example for sensor cable...
Page 65: ......
Page 66: ......
Page 70: ......