PART III: OPERATION
25
Fig. 14 - Burner control panel
Keys
S1
Main switch (0=Off, 1=GAS, 2=OIL)
S2
Reset pushbutton for control box
S3
CMF switch (0=stop, 1=low flame, 2=high flame, 3=automatic) - fully modulating burners only
D
Gas proving system reset pushbutton (only for burners with Siemens LDU11 provided)
B1
Lock-out LED
B2
Hi-flame operation LED
B3
Lo-flame operation LED
B4
“Ignition transformer operation” LED
B5
“Fan motor overload tripped” LED
B6
Stand-by signalling lamp
G1
Gas valves EV2 operation signalling lamp
G2
Gas valves EV1 operation signalling lamp
G3
Gas pressure switch signal lamp
G4
Gas proving system lockout signalling lamp
O5
Oil valve EVG operation signalling lamp
A2
AZL..
Gas operation
Check the gas feeding pressure is sufficient (signalling lamp
G3
on).
the gas proving system test begins; when the test is performed the proving system LED turns on. At the end of the test, the burner
staring cycle begins: in case of leakage in a valve, the gas proving system stops the burner and the lamp
B1
turns on.
NOTE:
if the burner is fitted with Dungs VPS504, the pre-purgue phase starts once the gas proving system is successfully performed.
Since the pre-purgue phase must be carried out with the maximum air rate, the control box drives the actuator opening and when the
maximum opening position is achieved, the pre-purge time counting starts.
At the end of the pre-purge time, the actuator drives the complete closing (ignition with gas position) and, as this is achieved the
ignition transformer is energised (LED
B4
is on); the gas valves open.
Few seconds after the valves opening, the transformer is de-energised and lamp
B4
turns off.
The burner is now operating, meanwhile the actuator goes to the high flame position and, after some seconds, the two-stage ope-
ration begins; the burner is driven automatically to high flame or low flame, according to the plant requirements.
Operation in high or low flame is signalled by lamp
B2
on the frontal panel.
B1
B6
B2 B3
B4
B5
G3
G2
G4
G1
O5
S2
S3
S1
A2
Summary of Contents for HTP2000
Page 13: ...PART I SPECIFICATIONS 13 Gas pressure in combustion head kW...
Page 35: ...PART III OPERATION 35 Pump flow rate Nozzle flow rate...
Page 45: ...PART IV MAINTENANCE 45...
Page 46: ...PART IV MAINTENANCE 46...
Page 47: ...PART IV MAINTENANCE 47...
Page 49: ...Siemens LMV5x Service Manual M12920CC rev 2 1 08 2017...
Page 56: ...8...
Page 60: ...12 2 2 LMV5x program structure...
Page 87: ...39...
Page 94: ......
Page 95: ......
Page 96: ...Note Specifications and data subject to change Errors and omissions excepted...
Page 98: ...Annex1 Example for motor cable...
Page 99: ......
Page 100: ...Annex 2 Example for sensor cable...
Page 101: ......
Page 102: ......
Page 106: ......