4. INSTALLATION
4.1 OFF LOADING AND INSPECTION
C-Series cyclone units are shipped with major
components mounted on skids. The blower assembly
will be pre-assembled to the upper barrel assembly.
The orientation will have the inlet and outlet opposed
180° unless requested otherwise at the time of order.
Other skids may contain afterfilter units or other
accessory components.
Inspection Note:
Upon receipt of your unit, check for any shipping
damage. A damaged carton indicates that the
equipment may have received rough handling during
shipping that may have caused possible internal
damage. Notify your delivery carrier and enter a
claim if any damage is found.
!
WARNING
Figure 3. Recommended Minimum Clearance
• Do not locate dust collector near dust source in
cases where the dust is explosive or a fire hazard.
• In preparing to install the unit, ensure location is
clear of all obstructions, such as utility lines or
roof overhangs.
4.2 INSTALLATION PLANNING
Selecting the proper location for your dust collection
equipment is very important. See Figure 2 for typical
installation details.
Certain items should be considered when locating
the unit, such as: room to empty the dust storage
container(s) or hoppers; shortest run for location of
ductwork; electrical connections; wall penetrations;
fan discharge direction; afterfilters. Ease of
maintenance should also be considered when
selecting the location and orientation of the system
(see Figure 3).
CYCFIG3
Revised 06/07
C-Series
Cyclone Dust Collector
5
Summary of Contents for C Series
Page 1: ...High Efficiency C Series Cyclone Dust Collector OWNER S MANUAL ...
Page 7: ...Figure 2 Typical Installation Diagram CYCFIG2 Revised 06 07 C Series Cyclone Dust Collector 4 ...
Page 19: ...Figure 13 Wiring Diagram 04 1534 Revised 06 07 C Series Cyclone Dust Collector 16 ...
Page 31: ...28 Revised 06 07 C Series Cyclone Dust Collector This page intentionally left blank ...