ROTARY AIRLOCK INSTALLATION
If a rotary airlock was ordered with the unit, the
hopper discharge will have a throw-out bin adapter
on the cone discharge. In most cases, the throw-out
bin will already be bolted to the adapter (see Figure
11). Ensure that the bolts connecting the adapter and
the throw-out bin to the cone discharge are securely
tightened.
Remove all packing from the rotary airlock and
determine its appropriate position. Keep in mind
required clearances, electrical connections and
maintenance. Apply sealant to the flange of the
rotary airlock and fasten to the adapter using 3/8"
bolt, nuts, lock washers.
DUCT SILENCER INSTALLATION
A duct-type silencer is designed to screw directly to
the fan outlet transition. Make sure there is adequate
room for the silencer in the direction of discharge.
Provide at least 24" of unobstructed space at the
end of the silencer discharge. The air discharge
should be directed into an open area free of
obstructions and with consideration for personnel
safety.
The silencer will require separate support. DO NOT
use the fan transition to support the silencer. Apply
silicone around the outside of the transition, lift the
silencer into position and secure with sheet metal
screws. Install permanent supports (not supplied by
UAS) and tighten all hardware before removing the
lifting device.
DRUM LID INSTALLATION
Remove the drum lid package from its shipping
carton. Place the drum lid on a standard 55 gallon
drum. Slide the 8" hose over the drum lid and secure
with a hose clamp. Position the drum assembly(s)
under the unit, slide the hose up onto the discharge
adapter collar on the cone and secure with a hose
clamp (see Figure 12).
C-SERIES AFTERFILTER ASSEMBLY
NOTE:
Familiarize yourself with components as
shown in Figures 9 and 10. Do not tighten
bolts until all posts and panels are in place.
Position hopper/leg assembly. Note slide gates and
orient the slide for easy access for dust drum
removal.
Install two corner posts in back left and back right
corners. Secure with 3/8" -16 x 1" hex head bolts,
3/8" lock washers and 3/8" flat washers. Orient posts
over bolt hole locations as shown in drawing.
Install one corner post with door hinge attached in
front left corner. Secure with 3/8" - 16 x 1" hex head
bolts, 3/8" lock washers and 3/8" flat washers.
Install front center panel (models C18 and C27).
Orient panel as shown in Figure 9. Secure top and
bottom with 3/8" - 16 hardware.
Install rear center panel (models C18 and C27).
Orient panel using the same bolt hole alignment as
the corner posts.
Install two side and two rear weather panels (see
Figure 9). Secure with 5/16" - 18 x 1" bolts, flat
washers, lock washers and nuts (eight sets per
panel). Hand tighten the hardware.
Install two weather door weldments. Secure with
5/16" - 18 x 1/2" pan head screen, 5/16" flat
washers, 5/16" lock washers and 5/16" - 18 nut (five
sets per panel). Hand tighten the hardware. Attach
fluted male knob into weld nuts in center post.
NOTE:
If threaded knob binds in door slot, loosen
pan head bolt/nuts and adjust door upward to
position door so knobs thread easily. Tighten
pan head bolt/nuts.
Tighten all fittings.
Raise plenum assembly with hydraulic lift truck forks
(or other suitable means) and set on top of corner
post with bolt holes aligned. Secure with 3/8" - 16
hardware as before with plenum supported. Leave
hardware hand tightened until all hardware is in
place. Tighten all hardware connections. Remove
support.
Install snap ring bags. Hold the end of the bag and
flex the “snap ring” at the bag end to seat the ring in
the plenum assembly. Start at the back corner of the
unit. Repeat this procedure for the snap ring on the
other end of the bag to seat it in the hopper
tubesheet. Repeat this procedure for each bag.
Ensure each snap ring is firmly seated in its
respective tubesheet hole (see Figure 8). Continue
working toward the front of the unit until all bags are
installed.
!
WARNING
All electrical connections must be performed by a
qualified electrician according to all applicable codes.
Refer to the nameplate and/or attached documentation
for voltage, amperage, cycle and proper wiring.
Figure 8.
Installation of Filter Bag in Tubesheet
Revised 06/07
C-Series
Cyclone Dust Collector
12
Summary of Contents for C Series
Page 1: ...High Efficiency C Series Cyclone Dust Collector OWNER S MANUAL ...
Page 7: ...Figure 2 Typical Installation Diagram CYCFIG2 Revised 06 07 C Series Cyclone Dust Collector 4 ...
Page 19: ...Figure 13 Wiring Diagram 04 1534 Revised 06 07 C Series Cyclone Dust Collector 16 ...
Page 31: ...28 Revised 06 07 C Series Cyclone Dust Collector This page intentionally left blank ...