4. Installation instructions
Step 1
:
base frame assembly
Assembly material specification and quantity
:
aluminum1
40*40*780 4PCS
aluminum2
40*20*660 2PCS
aluminum3
40*20*630 2PCS
Corner code
20PCS
screws M4*8
40PCS
gasket M4
40PCS
boat nuts M4
40PCS
screws M5*45
8PCS
1
2-aluminum1
4
1-aluminum2
M5*45
M5*45
2-aluminum3
Four countersunk
holes facing upward
on the surface
M4*8 M4 gasket boat nuts
Corner codes can be installed with
20 standby codes at a time
3
2-aluminum1
M5*45
M5*45
2
Note:
Installation
corner codes
should be kept
parallel and
vertical between
each aluminium
profile without
clearance.
Adjustment of
M5*45 can be
loosened slightly
before locking.
Slightly lock M5*45 screw for
easy follow-up adjustment
M6 threaded
hole Upward
M6 threaded hole
Upward
M6 threaded
hole Upward
M6 threaded hole
Upward
Installation corner codes in the connection of aluminium
profiles, it is necessary to keep the vertical and parallel
locking angle codes between the various aluminium
profiles.
The first step is to install the frame. After the
installation, the frame is assembled with the
second step, as shown in the figure.
Summary of Contents for X5SA-500-PRO
Page 1: ......
Page 22: ...17 5 Interface operation and printing ...
Page 26: ...2 How to use slice software Type setting follow the steps below to complete the setting 21 ...
Page 31: ......
Page 32: ......