background image

6

t150z pumped thermostatic electric shower

Table A

Table B

MCB

30/32A

32A
40A
40A
40A

40/45A

45A

cartridge

fuse

30A
35A
35A
45A
45A
45A
45A

unit 

rating

7.0kW
7.5kW
8.0kW
8.5kW
9.0kW
9.5kW

10.5kW

CIRCUIT PROTECTION

E-002-A

The installation, supply cable and circuit 
protection must conform with 

BS 7671

 (IEE 

wiring regulations) and be sufficient for the 
amperage required.
The following notes are for guidance only:

1

 

The shower must only be connected to a 
230-240V ac supply. If you are installing a 
shower with a kilowatt rating above 9kW, it 
is advisable to contact the local electricity 
supply company.

1.1

  The electrical rating of the shower is shown 

on the rating label 

(Fig.3)

 within the unit.

2

 

 Before making any sort of electrical 
connection within the installation make sure 
that no terminal is live. If in any doubt, 
switch off the whole installation at the mains 
supply and remove the correct fuse.

3

 

The shower must be connected to its own 
independent electrical circuit. 

IT MUST NOT

be connected to a ring main, spur, socket 
outlet, lighting circuit or cooker circuit.

3.1

  The electrical supply must be adequate for 

the loading of the unit and existing circuits.

4

 

Check your consumer unit (main fuse box) 
has a main switch rating of 80A or above 
and that it has a spare fuse way which will 
take the fuse or Miniature Circuit Breaker 
(MCB) necessary for the shower 

(Fig.4).

4.1

  If your consumer unit has a rating below 

80A or if there is no spare fuse way, then the 
installation will not be straightforward and 
may require a new consumer unit serving 
the house or just the shower.

4.2

  You will need to contact the local electricity 

company. They will check the supply and 
carry out what is necessary. 

5

 

For close circuit protection 

DO NOT

 use a 

rewireable fuse. Instead use a suitably rated 
Miniature Circuit Breaker (MCB) or cartridge 
fuse

(see Table A).

5.1

  A 30mA residual current device (RCD) must 

be installed in all UK electric and pumped 
shower circuits. This may be part of the 
consumer unit or a separate unit.

6

 

A 45 amp double pole isolating switch with 
a minimum contact gap of 3 mm in both 
poles must be incorporated in the circuit.

6.1

  It must have a mechanical indicator showing 

when the switch is in the 

OFF

position, and 

the wiring must be connected to the switch 
without the use of a plug or socket outlet.

6.2

  The switch must be accessible and clearly 

identifiable, but out of reach of a person 
using a fixed bath or shower, except for the 
cord of a cord operated switch, and should 
be placed so that it is not possible to touch 
the switch body while standing in a bath or 
shower cubicle. It should be readily 
accessible to switch off after using the 
shower.

7

 

Where shower cubicles are located in any 
rooms other than bathrooms, all socket 
outlets in those rooms must be protected by 
a 30mA RCD.

8

 

The current carrying capacity of the cable 
must be at least that of the shower circuit 
protection

(see Table B).

8.1

  To obtain full advantage of the power 

provided by the shower, use the shortest 
cable route possible from the consumer unit 
to the shower.

8.2

  It is also necessary to satisfy the 

disconnection time and thermal constraints 
which means that for any given combination 
of current demand, voltage drop and cable 
size, there is a maximum permissible circuit 
length.

9

 

The shower circuit should be separated from 
other circuits by at least twice the diameter 
of the cable or conduit.

9.1

  The current rating will be reduced if the 

cabling is bunched with others, surrounded 
by thermal loft or wall insulation or placed in 
areas where the ambient temperature is 
above 30°C. Under these conditions, 
derating factors apply and it is necessary to 
select a larger cable size.

9.2

In the majority of installations, the cable 
will unavoidably be placed in one or more 
of the above conditions. This being so, it 
is strongly recommended to use a 
minimum of 10mm cabling throughout 
the shower installation.

9.3

  In any event, it is essential that individual 

site conditions are assessed by a competent 
electrician in order to determine the correct 
cable size and permissible circuit length.

E-002-A

The installation, supply cable and circuit 
protection must conform with 

BS 7671

 (IEE 

wiring regulations) and be sufficient for the 
amperage required.
The following notes are for guidance only:

1

 

The shower must only be connected to a 
230-240V ac supply. If you are installing a 
shower with a kilowatt rating above 9kW, it 
is advisable to contact the local electricity 
supply company.

1.1

  The electrical rating of the shower is shown 

on the rating label 

(Fig.3)

 within the unit.

2

 

 Before making any sort of electrical 
connection within the installation make sure 
that no terminal is live. If in any doubt, 
switch off the whole installation at the mains 
supply and remove the correct fuse.

3

 

The shower must be connected to its own 
independent electrical circuit. 

IT MUST NOT

be connected to a ring main, spur, socket 
outlet, lighting circuit or cooker circuit.

3.1

  The electrical supply must be adequate for 

the loading of the unit and existing circuits.

4

 

Check your consumer unit (main fuse box) 
has a main switch rating of 80A or above 
and that it has a spare fuse way which will 
take the fuse or Miniature Circuit Breaker 
(MCB) necessary for the shower 

(Fig.4).

4.1

  If your consumer unit has a rating below 

80A or if there is no spare fuse way, then the 
installation will not be straightforward and 
may require a new consumer unit serving 
the house or just the shower.

4.2

  You will need to contact the local electricity 

company. They will check the supply and 
carry out what is necessary. 

5

 

For close circuit protection 

DO NOT

 use a 

rewireable fuse. Instead use a suitably rated 
Miniature Circuit Breaker (MCB) or cartridge 
fuse

(see Table A).

5.1

  A 30mA residual current device (RCD) must 

be installed in all UK electric and pumped 
shower circuits. This may be part of the 
consumer unit or a separate unit.

6

 

A 45 amp double pole isolating switch with 
a minimum contact gap of 3 mm in both 
poles must be incorporated in the circuit.

6.1

  It must have a mechanical indicator showing 

when the switch is in the 

OFF

position, and 

the wiring must be connected to the switch 
without the use of a plug or socket outlet.

6.2

  The switch must be accessible and clearly 

identifiable, but out of reach of a person 
using a fixed bath or shower, except for the 
cord of a cord operated switch, and should 
be placed so that it is not possible to touch 
the switch body while standing in a bath or 
shower cubicle. It should be readily 
accessible to switch off after using the 
shower.

7

 

Where shower cubicles are located in any 
rooms other than bathrooms, all socket 
outlets in those rooms must be protected by 
a 30mA RCD.

8

 

The current carrying capacity of the cable 
must be at least that of the shower circuit 
protection

(see Table B).

8.1

  To obtain full advantage of the power 

provided by the shower, use the shortest 
cable route possible from the consumer unit 
to the shower.

8.2

  It is also necessary to satisfy the 

disconnection time and thermal constraints 
which means that for any given combination 
of current demand, voltage drop and cable 
size, there is a maximum permissible circuit 
length.

9

 

The shower circuit should be separated from 
other circuits by at least twice the diameter 
of the cable or conduit.

9.1

  The current rating will be reduced if the 

cabling is bunched with others, surrounded 
by thermal loft or wall insulation or placed in 
areas where the ambient temperature is 
above 30°C. Under these conditions, 
derating factors apply and it is necessary to 
select a larger cable size.

9.2

In the majority of installations, the cable 
will unavoidably be placed in one or more 
of the above conditions. This being so, it 
is strongly recommended to use a 
minimum of 10mm cabling throughout 
the shower installation.

9.3

  In any event, it is essential that individual 

site conditions are assessed by a competent 
electrician in order to determine the correct 
cable size and permissible circuit length.

Circuit Protection

Note: 

Cable selection is dependent on 

derating factors

Twin and earth PVC insulated cable

Current carrying capacity

In conduit

trunking

6 mm²

38A

10 mm²

52A

16 mm²

69A

Installed in an 

insulated wall

6 mm²

35A

10 mm²

47A

16 mm²

63A

Clipped direct

or buried in a 

non-insulated 

wall

6 mm²

47A

10 mm²

64A

16 mm²

85A

Summary of Contents for t150z

Page 1: ...hese instructions are to be left with the user t150z pumped thermostatic electric shower IMPORTANT Under NO circumstances must this shower be connected directly to a mains water supply It is designed for GRAVITY FED COLD WATER systems ONLY Failure to comply may invalidate product warranty ...

Page 2: ... 1 Introduction 2 Specifications 2 Advice to users 2 Main components 3 4 Electrical requirements 5 6 Water requirements 7 Siting of the shower 8 Fitting the shower to the wall 9 Plumbing connections 10 11 Electrical connections 12 Shower drain pumps not supplied 13 14 Commissioning 15 16 PCB Dip Switch settings 17 Replacing the cover 18 Operating the shower Operating functions 19 21 Instructions f...

Page 3: ...t to operate This product is not suitable for mounting into steam rooms or steam cubicles PLUMBING The plumbing installation must comply with Water Regulations Building Regulations or any particular regulations as specified by Local Water Company or Water Undertakers and should be in accordance with BS 6700 The supply pipe must be flushed to clear debris before connecting to the shower unit DO NOT...

Page 4: ...w rate The temperature control can be adjusted to provide shower temperatures between 35 C and 47 C Alternatively adjusting a temperature stop mechanism inside the unit to 38 C 41 C or 43 C maximum can restrict the shower temperature Important To comply with BEAB care mark requirements the unit must not be able to run hotter than 41 C this is used in healthcare or special needs environments The T1...

Page 5: ... Top cable pipe entry 2 Wall screw fixings 3 Cover screw fixings 4 Thermal safety cut out 5 Power printed circuit board 6 Can and element assembly 7 Flow switch assembly 8 Temperature Control 9 Terminal block 10 Earth connection 11 Solenoid valve 12 Water inlet 13 Pressure relief device PRD 14 Shower outlet 15 Filter 16 Pump motor 17 Pump 18 Trimplate 19 Bottom cable pipe entry MAIN COMPONENTS 2 2...

Page 6: ...mostatic electric shower Inside Cover fig 2 20 Stop start switch Inside 21 Control printed circuit board Inside 22 Front cover T150Z pumped Other items Instructions guarantee etc MAIN COMPONENTS continued 20 21 22 Fig 2 ...

Page 7: ... independent electrical circuit IT MUST NOT be connected to a ring main spur socket outlet lighting circuit or cooker circuit 3 1 The electrical supply must be adequate for the loading of the unit and existing circuits 4 Check your consumer unit main fuse box has a main switch rating of 80A or above and that it has a spare fuse way which will take the fuse or Miniature Circuit Breaker MCB necessar...

Page 8: ... minimum of 10mm cabling throughout the shower installation 9 3 In any event it is essential that individual site conditions are assessed by a competent electrician in order to determine the correct E 002 A 6 1 It must have a mechanical indicator showing when the switch is in the OFF position and the wiring must be connected to the switch without the use of a plug or socket outlet 6 2 The switch m...

Page 9: ...There must be a maximum head of water of 10 metres and a minimum head of 8 cm as measured between the bottom of the cistern and the top of the shower unit There must be no other cold water draw offs between the cistern and the unit and the pipe must not supply water to any other tap or fitting at a lower level Note The supply pipe from the cistern should be on the opposite side to the float operat...

Page 10: ... double check valve or similar must be fitted in the supply pipework to prevent back flow Pressure relief safety device A pressure relief device PRD is designed into the shower unit which complies with European standards The PRD provides a level of appliance protection should an excessive build up of pressure occur within the shower Do not operate the shower with a damaged or kinked shower hose or...

Page 11: ...m of the cover fig 9 After choosing the site for the shower use the Installation Template supplied to mark the four fixing holes the position of which are shown in fig 7 Drill and plug the wall An appropriate drill bit should be used If the wall is brick plasterboard or a soft building block appropriate wall plugs and screws should be fitted Screw the top two fixing screw into position leaving the...

Page 12: ...onnection of the water supply to the inlet of the shower flush out the pipework to remove all swarf and system debris This can be achieved by connecting a hose to the pipework and turning on the water supply long enough to clear the debris to waste Procedure Turn off the water supply isolating stopvalve Connect the water supply to the Inlet of the shower via 15mm copper stainless steel or plastic ...

Page 13: ...ng only Do not use push fit connectors as full engagement cannot be guaranteed Do not use excessive force when making these connections Make sure the backplate is square on the wall and tighten the retaining screws which hold it to the wall Turn on the water supply and check for leaks in the pipework connection to the shower Note At this stage no water can flow through the unit Important Using a s...

Page 14: ... through conduit or in trunking or by embedding in the wall in accordance with IEE regulations The use of connections within the unit or other points in the shower circuit to supply power to unspecified equipment other than that listed on page18 will invalidate the guarantee DO NOT switch on the electricity supply until the cover has been fitted 1 Terminal block 2 Earth post 3 Start stop switch 4 ...

Page 15: ...etails of operation WARNING The pump is a non gravity installation It is advised that where the property is left unattended for an extended period of time that the water supply to the shower is shut off CONNECTING THE CONTROL WIRE The showers internal Pump Control Wire electrical connector is shown in fig 14 Note Numbers 1 and 2 only cover connecting the outgoing wire within the shower Please refe...

Page 16: ...tray 3 PRIMO XTRA 05PP01B With USG1 WH gully to suit a wet floor former 4 PRIMO XTRA 05PP01C With CSG1 gully for screed floors Technical Helpline 01606 592 586 E mail sales contour showers co uk For Contour Showers Pump information please visit www contour showers co uk NICHOLLS and CLARKE Ltd 1 P6821619 Phlexiflow Twinned pump waste system bottom exit tray kit 2 P6821620 Phlexiflow Twinned pump w...

Page 17: ...approximately 30 60 seconds is advised until a steady stream of water with no bubbles in it flows from the bleed screw Once this has been achieved re tighten the bleed screw Refit the right hand trimplate and the cover fig 16 17 DO NOT connect the PCB cable at this time This will allow the unit to operate in commissioning mode This allows the pump to operate but does not engage the heater can circ...

Page 18: ...trapped air Stop the shower using the isolating switch Remove the cover connect the PCB ribbon cable fig 20 refit the cover and secure using all of the retaining screws Adjusting the Maximum temperature stop The temperature control valve has an adjustable maximum temperature stop mechanism that is supplied factory set for 47 C This must be set to 41 C maximum if BEAB Care criteria needs to be met ...

Page 19: ... switch 1 On Audible Feedback On DIP switch 1 Off Audible Feedback Off DIP switch 2 Off Timed Shutdown 5 Mins DIP switch 3 Off DIP switch 2 Off Timed Shutdown 10 Mins DIP switch 3 On DIP switch 2 On Timed Shutdown 20 Mins DIP switch 3 Off DIP switch 2 On Timed Shutdown 30 Mins DIP switch 3 On DIP switch 4 Spare ON ED 1 2 3 4 ON ED 1 2 3 4 ON ED 1 2 3 4 ON ED 1 2 3 4 ON ED 1 2 3 4 ON ED 1 2 3 4 Fac...

Page 20: ...fully tightened c Make sure pipe and cable entering the unit do not prevent the cover locating correctly to the backplate Offer the cover to the unit Guide into position so that the knob spindle locates correctly minor adjustment may be necessary to align the knob and spindle Should any difficulty arise re check the points above While applying slight pressure to the cover secure in position with t...

Page 21: ... will cease to flow after a few seconds fig 21 To stop the shower timed Shutdown Shutdown times can be set at 5 10 20 factory setting or 30 minutes When the indicator illuminates it indicates there is 1 minute before the timed shutdown will turn the shower off Start Stop button Fig 21 Warning This appliance is not intended for use by persons including children with reduced physical sensory or ment...

Page 22: ...er numbers and make the water cooler To increase the shower temperature Turn the temperature control clockwise this will decrease the flow of water through the shower and is indicated by higher numbers and make the water hotter When the start stop button is pressed water will continue to flow in order to remove heated water inside the unit see phased shutdown process P21 Water will cease to flow a...

Page 23: ...ter will continue to flow for a few seconds flushing out any remaining hot water This makes sure the next immediate user will not receive a slug of hot water if standing under the showerhead when starting the shower Temperature Protection During normal operation if the flow of water through the unit is restricted power to the elements will be reduced to maintain the shower temperature When the flo...

Page 24: ...ation is carried out by a competent person Switch off the electricity and water supply to the shower The inlet filter is situated inside the water inlet fitting fig 24 To gain access to the filter remove the cover and right hand trim plate Unscrew the cap on the water inlet fitting Inspect the O ring for damage when the filter is removed Do not over tighten the filter cap on reassembly When cleani...

Page 25: ...ch assembly S19521007 6 Temperature Control assembly S19520805 7 Terminal block and wires S23410901 8 Solenoid valve assembly P23410801 9 Water inlet assembly P23411001 10 Pressure relief device PRD 82800450 11 Shower outlet reservoir P23410802 12 Access trimplate 7053949 13 Heater inlet valve assembly 8 5Kw S19520806 9 5Kw S19520808 14 Motor and pump assembly P15211002 15 Inlet filter assembly P2...

Page 26: ...id outlet elbow assembly not shown P23410803 Heater can wire set not shown 83313440 Triac and wires not shown P19520903 Thermister not shown 22012030 16 Front cover PCB 7073708 17 T150Z Pumped Front cover assembly S23410600 includes PCB and start stop switch SPARE PARTS 16 17 ...

Page 27: ...ved while commissioning 1 1 1 Blown fuse or circuit breaker Check supply Renew or reset fuse or circuit breaker If it fails again consult a qualified electrician 1 2 1 Power cut Check other appliances and if necessary contact local Electricity Supply Co 1 2 2 Have unit checked Ring Customer Service 1 3 1 The thermal cut out safety device has operated Have the unit checked by a suitably qualified s...

Page 28: ... thermistor failed 11 1 Power pcb faulty 6 1 1 Insufficient water flow available 1 Check showerhead is not blocked 2 Check shower hose is not restricted 3 Check filter is not blocked 4 Check water supply to shower is adequate 7 1 1 Shower will not start until water in the unit has cooled and LED goes off If problem persists 1 Check showerhead is not blocked 2 Check shower hose is not restricted 3 ...

Page 29: ...27 T150Z pumped thermostatic electric shower BEAB CARE requirements In service Testing T150Z pumped Designation Code IW S Shower ...

Page 30: ...tart button on the shower cover Identification Date of last calibration Supply water pressure Voltage Water temperature Note All installation commissioning and in service testing must be undertaken by a suitably qualified engineer With unit turned on set the temperature control to maximum temperature stop This test should be performed by measuring temperature from a gravity fed cold water tap Comm...

Page 31: ...t water temperature Checks made in accordance with Outlet water temperature when water supply is restricted Date of next in service check or withdrawal from service Signed dd mm yy Yes No Yes No Yes No ºC V ºC ºC dd mm yy Note All installation commissioning and in service testing must be undertaken by a suitably qualified engineer Check that the Maximum temperature stop is set to 41ºc See page 13 ...

Page 32: ...rvice valve should be returned to the fully open position after this test 4 Measurement of Supply Voltage at Appliance Terminals Switch off the electricity at the mains supply and remove the circuit fuse Remove the shower cover taking care to position it so that it does not hang by the interconnecting ribbon cable Replace the circuit fuse and switch on the electrical mains supply Take the AC volta...

Page 33: ...t in service test First in service test 6 to 8 weeks after commissioning If no significant change in water outlet temperature greater than 1 C between commissioning and first test 12 months after commissioning On going service testing Annually on the anniversary date when the unit was commissioned BEAB CARE requirements ...

Page 34: ...32 T150Z pumped thermostatic electric shower ...

Page 35: ...33 T150Z pumped thermostatic electric shower ...

Page 36: ...usly and expects customers to treat all staff members with respect Should any employee feel threatened or receive abuse either verbally or physically Triton reserves the right to withhold service and will support the employee with a legal prosecution Replacement Parts Policy Availability It is the policy of the manufacturer to maintain parts availability for the duration of production and a period...

Page 37: ...Pdf Supplied By http www plumbworld co uk ...

Reviews: