33
5. Installation
Figure 5-25A: Front view
5.5.2 Battery Installation and Connection
The 40 batteries can be divided into two groups connected in parallel for use. Each group has 20 batteries in series
(BAT+, N and BAT-). Place the batteries in the cabinet from the bottom to top one-by-one, then connect the battery cables
according to the diagrams that follow.
Note:
The positive and negative polarity of the battery cannot be reversed or short circuited. Doing so will damage the battery and/or cause
injury. Do not touch the battery’s positive and negative terminals at the same time. Before replacing or removing the batteries, disconnect
the breaker, pull up cell terminals and remove the screws of the copper bus bar. Not following the instructions could result in damage to the
equipment or personal injury. The installation must consist of 40 batteries.
Layer 3
Layer 4
Layer 2
Layer 1
Battery Group 2
Battery Group 1
Summary of Contents for BP240V100
Page 31: ...31 Figure 5 21 5 Installation Figure 5 22 11 Reinstall all covers and screws Figure 5 22...
Page 46: ...46 Figure 5 43 Model BP240V100L NIB Figure 5 44 5 Installation...
Page 47: ...47 Figure 5 45 12 Reinstall all covers and screws Figure 5 45 5 Installation...
Page 60: ...60 6 Operation and Configuration of S3M UPS Models and Battery Cabinets...
Page 114: ...114 Figura 5 43 Modelo BP240V100L NIB Figura 5 44 5 Instalaci n...
Page 115: ...115 Figura 5 45 12 Vuelva a instalar todas las cubiertas y tornillos Figura 5 45 5 Instalaci n...
Page 128: ...128 6 Operaci n y Configuraci n de Modelos de UPS S3M y Gabinetes de Bater as...
Page 183: ...183 Figure 5 43 mod le BP240V100L NIB Figure 5 44 5 Installation...
Page 198: ...198 6 Fonctionnement et configuration des mod les d onduleur S3M et des armoires de batteries...
Page 207: ...207...
Page 208: ...208 1111 W 35th Street Chicago IL 60609 USA tripplite com support 20 11 074 93 3BF8_RevB...