FIRST INSTALLATION
1. Before installation of the
STREAMLINER M
, the grease point (bearing and passage)
should be manually lubricated using a grease gun to ensure that the bearing can accept
grease. It is recommended that this procedure be conducted using either the same or a
compatible lubricant with what is contained in the grease pouch of the
STREAMLINER M
.
2. If any doubt exists, test the backpressure of the bearing with a grease gun connected to a
pressure gauge. Ensure that the break-off pressure is below 500 psi (approx. 35 kg-f/
㎠
:
34.5 bar). Note that it is always desirable to keep the constant delivery pressure as low as
possible.
3. Insert the
BATTERY PACK
into the battery compartment of main unit. (Make sure it is
locked after insertion.) Unscrew the cap of the
GREASE POUCH
. Fit the pouch outlet to
the pump suction inlet. Fit the top cover to main unit.
4. Turn the
STREAMLINER M
unit
ON
by depressing the
POWER
button for 2 seconds.
Confirm that the LCD is turned on by checking that the red LED blinks once. As long as the
LCD is displayed, the unit is working. To test that the unit is operational, simply follow the
TEST MODE
procedure :
Depress TEST button, the unit displays “tst” and start to discharge grease. The unit
will continuously operate in purge mode until the TEST button is depressed.
To deactivate TEST MODE, depress the button. The unit will stop functioning in
TEST MODE within 20 seconds. Otherwise, the unit will automatically stop TEST
MODE after 2 minutes and be back to previous mode set.
5. To set a required dispensing rate, depress the MODE button. The dispensing rate
changes in ascending frequency i.e. 1
☜
2
☜
3
☜
6
☜
12
☜
Half month.
6. Remove the grease nipple used for back pressure testing and fit an appropriate adaptor of
3/8” NPT or BSPT and make sure that the unit is well tightened to it. The 3/8” brass thread
of the unit ensures that fitting will not snap off even under severe vibration or shock load.
7. For installations that involve extreme vibration, excessive heat, or a service location
considered dangerous, use the remote mounting clamp assembly and a steel pipe or
copper tube of no less than 1/4” I.D. Remote installation over more than 1 meter may
reduce the ability of the unit to dispense against elevated backpressure.
IMPORTANT:
Be sure to fill the steel pipe or copper tube with lubricant prior to
installation.
8. STREAMLINER M
units have a shelf life of one-year with a one-year warranty from date
of delivery.
Page 7/11