10 Stove
Installation
(for qualified installers only)
© Travis Industries
100-01165
4110919
Hearth Requirements
Must extend in front of the insert and on both sides (see Insert Placement Requirements for details)
Must be non-combustible and at least .018" thick (26 gauge)
Drafting Performance
This appliance relies upon natural draft to operate. External forces, such as wind, barometric pressure, topography,
or factors of the home (negative pressure from exhaust fans, chimneys, air infiltration, etc.), may adversely affect
draft. Travis Industries cannot be responsible for external forces leading to less than optimal performance.
Insert Rollers
Two rollers are built into the back edge of the insert. This
allows the insert to be rolled into position by lifting the front
of the insert and pushing it into position (see
Figure 5
).
Figure 5
Leveling Bolt Installation
Two leveling bolts are pre-installed on the insert to allow
for proper leveling within the fireplace. To access the
bolts, remove the back corner firebricks and cover plates
(see
Figure 6
“a” and “b”). The bolts are pre-threaded to a
weld-nut on the base of the insert. Use a 3/4” socket
wrench to screw the bolts down (clockwise) until the insert
is level (see “c”).
MASONRY NOTE
: You may wish to place a metal plate
below the bolt if the masonry is weak.
SEALING THE COVER PLATE
: We recommend sealing
the cover plate with furnace cement (place on underside of
cover plate).
BOLT LENGTH
: The included bolts allow approximately 1”
of rise. If additional rise is required, use a longer 1/2-13
thread bolt. Make sure the additional bolt length does not
interfere with the cover plate.
Figure 6
a
b
c
3/4"