55
Transport, installation, commissioning
TNL12.2
DTE070EN - 15.09.2021
Commissioning
Switching on the machine
Before switching on the machine, the key switch must be in the
“Production mode”
position to prevent unexpected start-up or
unexpected movement.
Before initial commissioning, the machine owner is required to
check the safe condition of the machine, including its safety devic-
es. This must also be done during operation at reasonable regular
intervals, but at least after each repair and maintenance.
• Turn on from the main switch on the control cabinet.
• Switch on the NC controller from the machine operating panel.
• Press the
Reset
key
(any internally pending error messages are deleted).
• Open and close the work area door.
The functionality of the door switches must be checked by open-
ing and closing the work area door. Only if the safety devices
respond, the machine can be started.
Lock the work area door by pressing the
GUARD
key.
(The work area door must be manually locked and unlocked when setting up
the machine.
In automatic mode, the work area door can be locked with the
GUARD
or
AUTOMATIC START
key.
LED
status
on
The work area door is locked
off
The work area door is unlocked
flashes
The safety switch is blocked, or a secured cover/protective door
is not closed.
• Switch on the drives.
0
I
NC I
RESET
GUARD
Example shown
Summary of Contents for TNL12.2
Page 6: ...6 Transport and installation TNL12 2 DTE070EN 15 09 2021 Table of Contents ...
Page 8: ...8 Transport TNL12 2 DTE070EN 15 09 2021 Safety ...
Page 16: ...16 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 General ...
Page 32: ...32 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 Transporting the machine ...
Page 44: ...44 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 Installing the machine ...
Page 50: ...50 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 Electrical connection ...
Page 52: ...52 Transport Installation Commissioning TNL12 2 DTE070EN 15 09 2021 Pneumatic connection ...
Page 56: ...56 Transport installation commissioning TNL12 2 DTE070EN 15 09 2021 Commissioning ...
Page 61: ......