4. Installation and startup
4.1. Installation precaution
Warning
!
Before installation and maintenance, AC and DC side doesn’t carry
electricity, but if DC side is just disconnected, capacitance still contains
electricity, so please wait for at least 5 minutes to ensure the capacitors
completely release the energy and inverter is not electrified.
Note
!
Inverters must be installed by qualified person.
Trannergy assures the product guarantee of the TRB series inverters during five
years after your purchase, if the installation site does not meet the instructions
described in this manual, it is out of warranty. The warranty is limited to the costs
of repair and/or replacement of the product by Trannergy only.
Ventilation is very important to cool the inverter. For outdoors application, the
inverter requires at least 300mm of clearance among the other units and 300mm of
the ground or the roof. See Figure 4-1:
300mm
300mm
300mm
300mm
Figure 4-1 Distance required of Inverters
4.2. Install steps
Setp1
: Drill six Ø10 holes in the wall according to the dimensions shows in Figure
4-2: