Installation
Recessed vertical units (Option)
The optional recessing flange assembly
includes pre-cut flanges, corner transi-
tion pieces, mounting screws, filler
pieces and pressure sensitive gaskets.
Refer to
Figure 19
for a typical vertical
installation. To install the recessing
flange, complete the following proce-
dures:
1. Make certain both end covers are
secured to the unit.
2. Measure and cut the pressure
sensitive gaskets to the correct
lengths and attach to the flanges.
3. Starting at a corner, attach the top
flange with the metal cutting screws
provided.
4. Press the corner transition pieces
onto the end of the flange and
attach the adjoining flanges and
filler pieces at the bottom of the
unit. Work around the unit in this
manner until all flanges and corners
are installed.
5. Mounting holes are pre-drilled in
the flanges. Use the assembled
flanges as a template to drill all
7/32’’ mounting holes in the cabinet.
6. Attach the flange section to the unit
cabinet with the mounting screws
provided.
7. Open and remove the front acces
panel.
8. Set the unit in place and push it
tightly against the back support and
flush with the wall surface. Anchor
the unit to back supports, using the
1/2’’ mounting holes described in
the
Unit Mounting
section.
9. Tighten the mounting fastener,
making sure that the unit is level.
NOTE:
Unit must be mounted level.
Coils and drain pans inside the unit are
pitched properly for drainage before
shipment.
End Covers
When ordered as an option, end covers
ship already attached to the vertical
unit ventilator. The following section is
for installing end covers purchased as
an add-on.
It is recommended end panels be
installed on the unit ventilator after all
piping, wiring and accessory installa-
tion is completed.
To install the end panel:
1. Insert the four factory provided
metal studs into the four
pre-mounted nuts on the inside of
the panel.
2. Align each stud with the four pre-
drilled holes on the side of the unit.
3. Secure the panel to the unit by
fastening with the four factory
provided nuts.
4. Do not over-tighten screws.
CAUTION
Equipment Damage
Do not run units for any length of time
without all panels and filters properly
installed. Failure to do so may result in
equipment failure.
Gaskets
Recessing
Flanges
Corner
Transition Piece
Vertical Unit
Back
7/32" diameter holes
drilled for flange mounting
Figure 19:
Recess
flange installation
for vertical unit
ventilators
Summary of Contents for UV-SVN02B-EN
Page 38: ...38 UV SVN002 EN Wiring Diagrams Figure 44 Power Diagram For 480V 3 Phase 4 Wire Electric Heat...
Page 40: ...40 UV SVN002 EN Wiring Diagrams Figure 46 End Device Package 120V Hot Water DX Cooling...
Page 41: ...UV SVN002 EN 41 Wiring Diagrams Figure 47 208V or 240V 3 Phase 3 Wire Electric Heat DX Cooling...
Page 50: ...50 UV SVN002 EN Accessories Wall Boxes Figure 59 Vertical wallbox V1 V3 V2 V6 dimensions...