CTV-SVX06J-EN
21
☐
Carbon rupture disk and gaskets removed and
discarded.
☐
Proper adapters utilized with proper sealant
(Loctite
®
242 or Loctite
®
277) or welded.
☐
Excess flow valve installed horizontally; refer to
figures in
.
☐
Pressure gauge installed; refer to figures in
☐
Pressure switch installed (when selected); refer to
figures in
.
☐
Purge discharge line connected to the downstream
side piping to vent purge exhaust out the vent line
to the outdoors and no u-traps created in this line.
☐
Drip leg and drain present.
☐
Pressure test RuptureGuard
™
installation using 5
psig (34.5 kPaG) dry nitrogen.
☐
Chiller nitrogen holding charge applied (5 psig [34.5
kPaG]).