Unit Weight and Rigging
36
OAU-SVX004D-EN
Before proceeding, refer to tables in Unit Weight section
for typical unit operating weights and
for
rigging drawing.
1. Remove the shipping crate from around the unit.
2. Rig the unit as shown in
. Attach
adequate strength lifting slings to all four lifting
brackets in the unit base rail. Do not use cables, chains,
or slings except as shown.
3. Install a lifting bar, as shown in
, to
protect the unit and to facilitate a uniform lift. The
minimum distance between the lifting hook and the
top of the unit should be 7 feet.
4. Test-lift the unit to ensure it is properly rigged and
balanced, make any necessary rigging adjustments.
5. Lift the unit and position it into place. Remove fork
pockets prior to setting on the curb.
6. Downflow units; align the base rail of the unit with the
curb rail while lowering the unit onto the curb. Make
sure that the gasket on the curb is not damaged while
positioning the unit.
Figure 38.
Rigging (continued)
SCALE 1 : 12
DETAIL C
LIFTING POINTS
(4 LOCATIONS)
SPREADER BARS
LENGTH
WIDTH
4-point lift
Model: OAK
and OAN
SPREADER BARS
LENGTH
WIDTH
SCALE 1 : 12
DETAIL A
LIFTING POINTS
(6 LOCATIONS)
6-point lift
Model: OAK
and OAN
DETAIL A
SCALE 1 : 12
LIFTING POINTS
(8 LOCATIONS)
SPREADER BARS
LENGTH
WIDTH
8-point lift
Model: OAK
and OAN
Summary of Contents for Horizon OABE/F
Page 32: ...Unit Clearances Curb Dimensions and Dimensional Data 32 OAU SVX004D EN ...
Page 37: ...Unit Weight and Rigging OAU SVX004D EN 37 ...
Page 55: ...Installation OAU SVX004D EN 55 ...
Page 78: ...Performance Data 78 OAU SVX004D EN ...
Page 84: ...Appendix 84 OAU SVX004D EN Figure 79 BAYSENS036A installation instructions ...
Page 85: ...Appendix OAU SVX004D EN 85 Figure 80 VELCON 0351 installation instructions ...
Page 89: ...Appendix OAU SVX004D EN 89 ...
Page 90: ......
Page 91: ......