Trane CGCL 200 Installation Operation & Maintenance Download Page 14

General start-up

Start-up preparation

Carry out all operations on check list
and that the unit is correctly
installed and ready to operate.
The installer must check all the
following points before calling in the
Trane Servicing Department to put
the equipment into service:
- Check position of unit
- Check unit is level
- Check type and position of rubber

pads

- Check clearance required for

maintenance access (See submittals)

- Check clearance around condenser

(See Submittals)

- Chilled water circuit ready to

operate, filled with water, pressure
test carried out and air purged.

- Chilled water circuit must be rinsed
- Check the presence of water

strainer ahead of evaporator

- The strainers must be cleaned

after 2 hours of pumps operation

- Check the thermometers and

manometers position

- Check chilled water pumps

interconnection to control panel

- Insure that the isolation resistance

of all power supply terminals to
ground complies with standards
and regulations in force.

- Check that unit voltage and

frequency supplied match rated
input voltage and frequency

- Check that all electrical connections

are clean and sound - Check that
main power supply switch is sound.

- Check Ethylene glycol % in the

chilled water circuit if Ethylene
glycol presence is required.

- Check chilled water pressure drop

through evaporator is in
accordance with the Trane order
write-up.

- On start-up of each motor in the

system, check the direction of
rotation and operation of all the
components they drive

- Water flow control checking:

decrease the water flow and check
the electrical contact in the control
panel.

- Check that there is sufficient

demand for cooling on the day of
start-up (around 50% of nominal
load)

Start-up

Follow the instructions below to
correctly start-up the unit.

Installation and chiller inspection:
- Ensure that all the operations

above (start-up preparation), are
followed.

- Follow the instruction stuck inside

the electrical cabinet:

- Unscrew the screws securing the

isolators located under the rails
supporting the compressor.

- Put the plexiglass supplied by

Trane in front of the power terminal.

- Insure all water and refrigerant

valves are in service positions,

- Insure that the unit is not

damaged,

- Insure that sensors are properly

installed in their bulb-wells and
submerged in heat conducting
product,

- Check fixing of capillary tubes

(protection from vibration and
from wear) and insure that they
are not damaged,

- Reset all manually set control

devices,

- Check refrigerating circuits tightness

Checking and setting:
Compressors:
- Check oil level at rest. The level

should reach at least halfway up
indicator located on housing. 
See fig. 9 for correct level.

Figure 9 - Compressor oil level

1. Max. oil level
2. Min. oil level

- Check fixing of capillary tubes

(protection from vibration and
from wear) and insure that they
are not damaged,

- Reset all manually set control

devices,

- Check refrigerating circuits

tightness

- Check oil acidity,
- Check electrical terminals

tightening of the motors and in the
control panel,

- Check the isolation of the motors

using a 500V DC megohmeter
which meets manufacturer's
specifications (minimum value 2
meghoms)

- Check the direction of the rotation

using phasemeter.

Electrical power wiring:
- Check all the electrical terminals

tightening,

- Set-up compressors overload

relays,

- Set-up fan-motors overload relays,
Electrical control wiring:
- Check all the electrical terminals

tightening,

- Check all the pressostats,
- Check and set-up the CH530

control

- Test and start-up without the

electrical power.

Condenser:
- Check setting of the safety

pressure valve,

- Check direction of the rotation of

fans,

- Check the isolation of the motors

using a 500V DC megohmeter
which meets manufacturer's
specifications (minimum value 2
meghoms)

Operating parameters statement:
- Switch on main power supply

switch,

- Start the water pump(s),
- Start up the unit with CH530 by

pushing "Auto".

The unit and the chilled water
pumps contactor must be connected
together,
- After unit start up, leave in

operation for at least 15 minutes,
to insure pressures are stabilized.

Then check:
- voltage,
- compressors and fan-motors

currents,

- leaving and return chilled water

temperature,

- suction temperature and pressure,
- ambient air temperature,
- blowing air temperature,
- discharge pressure and temperature.

1

2

14

CGCL-SVX01B-E4

Summary of Contents for CGCL 200

Page 1: ...Installation Operation Maintenance CGCL Air Cooled Water Chiller With Centrifugal Fans Sizes 200 250 300 350 400 450 500 600 CGCL SVX01B E4...

Page 2: ...structor assumes no liability for installations or servicing performed by unqualified personnel WARNING Indicates a potentially hazardous situation which if not avoided could result in death or seriou...

Page 3: ...laiming for the described damage A copy of this letter must be sent toTrane Epinal Operations Claims team Warranty Warranty is based on the general terms and conditions of the manufacturer The warrant...

Page 4: ...ailure to respect these installation and maintenance instructions may result in immediate cancellation of the warranty Training To assist you in obtaining the best use of it and maintaining it in perf...

Page 5: ...porator connection 11 Minimum water volume 11 Water treatment 12 Antifreeze protection 12 Electrical connections 13 General start up Start up preparation 14 Start up 14 Operation Unit operation 16 Wee...

Page 6: ...s 2 A 139 194 203 212 221 230 240 258 Motor RPM rpm 2900 2900 2900 2900 2900 2900 2900 2900 Sump heater 2 W Evaporator Number 1 Type Brazed plate Water volume total l 4 7 5 9 7 0 8 2 10 5 10 5 12 3 16...

Page 7: ...Nominal Power High Speed KW 11 0 15 0 15 0 Nominal Amps Low speed A 7 7 10 1 10 1 Nominal Amps High speed A 21 5 28 6 28 6 Starting Amps A 33 43 43 CGCL 600 47600 Fan Motor Nominal Power Low Speed kW...

Page 8: ...to isolate the base from the ground 4 pads for the sizes 200 to 300 6 pads for the sizes 350 to 600 Trane does not allow to install spring isolators 8 CGCL SVX01B E4 Selection of the Proper Available...

Page 9: ...xing screws do not pierce the coil Figure 2 1 Accessory 2 Attachment bolts 3 Unit frame 4 Sealing strip 5 Accessory filter Figure 3 Inlet 1 Unit body 2 Flexible coupling 3 Ductwork 4 Seal 4 1 2 3 CGCL...

Page 10: ...tion connected to a fan must have at least the same cross sectional area as the output panel orifice and its minimum length must be one and a half times the fan diameter before any bend or deviation T...

Page 11: ...ume Why the water volume is an important parameter The water volume is an important parameter because it allows a stable chilled water temperature and avoids short cycle operation of the compressors P...

Page 12: ...e to the use of untreated or improperly treated water or from the use of saline or brackish water If required contact your localTrane Sales Office Antifreeze protection During negative ambient air tem...

Page 13: ...he type and location of fuses must also comply with standards As a safety measure fuses should be visibly installed close to the unit 2 Only copper wiring should be used Using aluminium wires can prod...

Page 14: ...upplied by Trane in front of the power terminal Insure all water and refrigerant valves are in service positions Insure that the unit is not damaged Insure that sensors are properly installed in their...

Page 15: ...id all the damage risks of the chiller and evaporator water pipes CAUTION For the warranty to apply any start up carried out directly by the customer must be recorded in a detailed report which must b...

Page 16: ...st Carry out oil analysis Record operating pressures temperatures amperages and voltage Check operation of machines compare conditions of operation against original commissioning data Stop the unit th...

Page 17: ...esence is required Check operational set points and performance Calibrate controls Check operation of all safety devices Inspect contacts and tighten terminals Megger the motor compressor windings Rec...

Page 18: ...r ahead of evaporator Check presence of air purge valve Check rinsing and filling of chilled water pipes Check water pump s contactor interconnected to control panel Check water flow Check chilled wat...

Page 19: ...itched off Fuse blown Voltage too low Control circuit open Compressor sticking damaged or sticking components Discharge pressure too high Dirty coil Not enough airflow Discharge pressure too high a Vo...

Page 20: ...e locked in open position Not enough refrigerant Drier filter clogged Superheat not properly adjusted Chilled water pipes obstructed Presence of uncondensable liquids in system or excess refrigerant O...

Page 21: ...t does not flow through thermostatic expansion valve Drier filter clogged Expansion valve bulb has lost its refrigerant Replace the filter drier Replace the bulb Loss of power Expansion valve obstruct...

Page 22: ...22 CGCL SVX01B E4 Notes...

Page 23: ...CGCL SVX01B E4 23 Notes...

Page 24: ...eserves the right to change design and specifications without notice Only qualified technicians should perform the installation and servicing of equipment referred to in this publication www trane com...