background image

30

Factory (initial) Oil-Charging
Procedure

The initial charging procedure
should be followed any time the unit
is new or has had all of the oil
removed.
1. Add 0.95 liter (0.90 kg) of oil to the

motor cavity or suction line prior
to installing the compressor into
the chiller.

2. If the unit is not equipped with

suction-line isolation valves, it
should contain no charge. If it has
isolation valves, then the charge
may be trapped in the evaporator.
In either case, the high side of the
system should not be pressurized.

3. The oil-line shutoff valve must be

open to allow the oil to pass into
the oil lines and the oil separator.

4. The oil charging port is a ¼"

[6 mm] flare fitting with a Schrader
valve that is on the side of the oil-
filter housing. This is the port that
must be used to add oil into the
compressor so that the filter and
lines are full at the first start of the
compressor.

5. On single-compressor circuits, all

the oil should be put into the
circuit through the oil-charging
port on the compressor filter
housing. On two-compressor
circuits, put approximately ½ of
the oil into the unit through each
of the two oil-charging ports on
the two compressors.

6. Oil may be put into the unit using

either of two methods:

C

CA

AU

UT

TIIO

ON

N

Use only Trane OIL 00048 in the units
to avoid any catastrophic damage to
the compressor or unit.

• Have the unit in vacuum. Note that

the vacuum connection should be
made on the unit at the service
valve that is on the discharge line.
Hook up one end of the oil-charging
hose to the oil-charging fitting and
immerse the other end into the oil
container. Let the vacuum draw the
required amount of oil into the unit.

• Have the unit at the same pressure

as the oil. Hook up one end of the

oil-charging hose to the oil-
charging fitting and the other end
to an oil pump. Use the pump to
draw oil out of the oil container and
push the required amount of oil
into the unit. Note: the compressor
filter has an internal shutoff valve
that will prevent oil from entering
the compressor while the
compressor is not running.
Therefore, there is no concern
about flooding the compressor with
oil.

Field Oil-Charging
Procedure

Use the initial charging procedure
under the following circumstances:

• When virtually all of the oil has

been removed.

• If the oil charge is removed from

the compressor and oil system
only, but the unit has been run for
less than 15 minutes.

• If the oil charge is removed from

the compressor and oil system
only, and the unit has been run for
more than 15 minutes. 

However, reduce the amount of oil
added to the unit by the normal
quantity of oil in the refrigeration
system. 

Note:

this procedure can be followed

even with the refrigerant charge
isolated in the evaporating section of
the unit.

If small quantities of oil were
removed to service refrigeration
components,

such as the evaporator,

replace the oil that was removed
back into the serviced component
prior to vacuum and recharge of the
refrigerant.

If oil was removed to service a
compressor or change the filter

follow this procedure:

1. If the compressor is a new

compressor or has been removed
from the system and reworked,
add 0.95 liter (0.90 kg) of oil to the
motor cavity prior to installing the
compressor into the chiller.

2. Install the compressor in the

system. Make sure that the filter

shutoff valve is closed. Other
compressor isolation valves may
also be closed depending upon
the service that was completed.

For example, changing the oil filter
would require the compressor to be
isolated and pulled into vacuum.
Note: Ensure that the compressor is
not pressurized.

3. Open the flare fitting on the oil-line

shutoff valve.

4. Open the flare fitting on the filter

housing. This is the port that must
be used to put oil into the
compressor.

5. Install one end of the charging

hose on the oil charging port (with
the Schrader valve) and the other
on the oil canister.

6. Lift the oil canister, or use a pump,

to pour oil into the filter housing.

7. When oil comes out of the flare

fitting on the oil-line shutoff valve,
the filter is full. Stop adding oil.

8. Put the cap on the flare on the oil-

line shutoff valve, remove the
charging hose, and put the cap
back on the flare on the filter
housing.

9. Vacuum the compressor (low side)

and prepare it for inclusion in the
system. There is a service valve on
the suction line and on the
evaporator. Use these valves to
vacuum the compressor.

10. Open the oil-line shutoff valve.

Severe damage to the
compressor can result if the oil-
line shutoff valve is closed when
the compressor is started.

C

CA

AU

UT

TIIO

ON

N

Catastrophic damage to the
compressor will occur if the oil-line
shutoff valve or the isolation valves
are left closed on unit startup.

11. Open the other compressor

isolation valves. 

Note:

this procedure assumes that

the oil that is put into the filter
housing does not have contaminants
such as non- condensable gases. The
oil forces these gases out of the filter

Maintenance

RLC-SVX03A-E4

Summary of Contents for 108-216

Page 1: ...Installation Operation Maintenance RTUB 207 224 Liquid chillers with helical rotary compressors RTCA 108 216 Remote air cooled condenser RLC SVX03A E4...

Page 2: ...delivery note and send a registered letter of protest to the last carrier of the goods within 72 hours of delivery Notify the localTrane Sales Office at the same time The unit should be totally inspe...

Page 3: ...a RTCA 8 Installation Installation Responsibilities 9 Storage 9 Special Lifting and Moving Instructions 10 Isolation 10 Foundation 10 Clearances 11 Drainage 12 Releasing the Nitrogen Holding Charge 12...

Page 4: ...Temporary Shutdown and Restart 23 Extended Shutdown Procedure 23 System Restart after Extended Shutdown 23 Maintenance Periodic Maintenance 25 Refrigerant and Oil Charge Management 27 R134a Field char...

Page 5: ...ane Sales Office Do not proceed with installation of a damaged unit without sales office approval Inspection Checklist To protect against loss due to damage incurred in transit complete the following...

Page 6: ...l for shipment Description of the Unit The RTUB units are liquid chillers equipped with two helical rotary compressors and an evaporator designed to operate with remote RTCA air cooled condensers or o...

Page 7: ...ng Weight kg 2130 2130 2845 2845 2845 3250 Shipping Weight kg 1860 1860 2570 2570 2570 2975 Unit size 216 217 218 220 222 224 Compressor Type Quantity Helical rotary 2 Nominal size tons 70 85 85 85 10...

Page 8: ...8 1 5 8 1 5 8 Liquid connection inches 1 1 8 1 1 8 1 1 8 1 1 8 1 1 8 1 1 8 Unit size 208 209 211 213 215 216 Condenser Condenser type Aluminium fins copper tubes Fin spacing fins ft 168 168 144 168 16...

Page 9: ...for RTUB Furnish and install strainers ahead of all pumps and automatic modulating valves Furnish and install check valves on the discharge lines between oil separators and condenser in order to avoi...

Page 10: ...e sound transmitted through water piping To reduce the sound transmitted through electrical conduit use flexible electrical conduit State and local codes on sound emissions should always be considered...

Page 11: ...igure 5 andTable 4 for unit Figure 5 Unit Dimensions and Recommended Minimum Clearances RTCA Figure 6 Unit Dimensions and Recommended Minimum Clearances RTUB A C D B A C D B Table 4 Unit Dimensions an...

Page 12: ...n transmission through the water lines If desired install thermometers in the lines to monitor entering and leaving water temperatures Install a balancing valve in the leaving water line to control wa...

Page 13: ...tween the water and system components Foreign matter in the chilled water system can also increase pressure drop and consequently reduce water flow Proper water treatment must be determined locally de...

Page 14: ...es for relief valve installation guidelines Installing and connecting temperature sensors General Recommendations Regardless of the type of monitoring sensor required by a particular application the s...

Page 15: ...ambient temperature and condenser temperature sensors must be connected to the RTUB to monitor it The ambient temperature sensor must be installed in a position which represents most accurately the c...

Page 16: ...its each with its own ventilation The ventilation cannot be common to the two circuits For this type of installation non RTCA condenser an On Off signal is available on the unit control module UCM of...

Page 17: ...commended to place a trap on the discharge line at the oil separator outlet if this discharge line is horizontal for a distance greater than 5 m at a height greater than the connection to the oil sepa...

Page 18: ...n the two units must not exceed 60 m in reality or the equivalent of 90 m taking into account pressure drops The height of the liquid line in relation to the condenser base must be less than 5 m Legen...

Page 19: ...uction line using the following criteria 1 2 5 m s minimum in the horizontal parts 2 5 0 m s minimum in the vertical parts 3 Maximum speed 20 m s The minimum slope of the suction line to the condenser...

Page 20: ...ent manometer must be installed upstream of the vacuum pump stop valve 1 Close valve B and open valve A After a few minutes the manometer reading indicated the lowest vacuum level that can be obtained...

Page 21: ...f untreated or improperly treated water or saline or brackish water Close the fused disconnect switch es that supplies power to the chilled water pump starter Start the chilled water pump to begin cir...

Page 22: ...ions prior to start up have been performed see previous sections the unit is ready to start Press the Stop key on the UCM CLD If necessary adjust the setpoint values in the UCM CLD reports refer to th...

Page 23: ...ain glycol to prevent any risk of evaporator freeze up Extended period shutdown The procedure below must be performed if the system has to be stopped for a prolonged period for example seasonal shutdo...

Page 24: ...Flow Rates and Water System Pressure Drop 7 Adjust the flow switch on the evaporator piping for proper operation 8 Stop the water pump The unit is now ready for startup as described in Startup Proced...

Page 25: ...even more if conditions are very poor or if corrosion damage begins to occur To clean the coils use a soft brush and a sprayer garden pump up type A high quality detergent such as Trane Coil Cleaner...

Page 26: ...ser 2 After the compressor stops close the compressor discharge valve and disconnect the unit Note Do not make successive vacuums by using the compressor Irreversible compressor damage could occur 3 V...

Page 27: ...line due to high vapor velocity High Condenser Subcooler Pressure drop Some symptoms of a refrigerant over charged unit High subcooling Larger than normal condenser approach temperatures Entering Con...

Page 28: ...tenance on the compressor or high side It is much more preferable to isolate the charge in the evaporator if this option is available High side charge isolation procedure 1 Make sure the circuit is of...

Page 29: ...he oil system is critical to the reliability of the compressor and chiller Too little oil can cause the compressor to run hot and inefficiently When taken to an extreme low oil level may result in inf...

Page 30: ...s than 15 minutes If the oil charge is removed from the compressor and oil system only and the unit has been run for more than 15 minutes However reduce the amount of oil added to the unit by the norm...

Page 31: ...tainer or is otherwise contaminated then this small volume must be subject to vacuum as well However the filter cavity is full of oil Therefore be sure to use a flash tank in line with the vacuum pump...

Page 32: ...stem should be carried out only by qualified and experienced personnel Maintenance contract It is strongly recommended that you sign a maintenance contract with your local Service Agency This contract...

Reviews: