105
G8000 Series Installation and Operation Manual
Appendix C - 500kVA Input- and Output- Cabinet Joining
Instructions
Joining the G8000 500kVA Sections
1. Remove Shipping Material (Retain Connection Kit Box and Manual).
2.
On a leveled floor bring the two cabinets together. Input cabinet on the left side. See
FIG. 1. Leave a gap of 0.25”-0.30” between the cabinets. See FIG. 2.
3.
4. On Input cabinet: Open the door, remove back panel (retain hardware). See FIG. 3.
Insert 1/2-13X1.75” bolt, flat & lock washer assembly (supplied); two in the front and
two in the back. See FIG. 4 & FIG. 5.
INPUT CABINET
OUTPUT CABINET
LEAVE A GAP OF 0.25”-0.30”
BETWEEN CABINETS
FIG. 1
FIG. 2
Summary of Contents for G8000 Series
Page 2: ......
Page 10: ...iv G8000 Series Installation and Operation Manual ...
Page 88: ...78 G8000 Series Installation and Operation Manual ...
Page 110: ...100 G8000 Series Installation and Operation Manual ...
Page 113: ...103 G8000 Series Installation and Operation Manual FIGURE B 3 G8000 300 KVA OUTLINE DRAWING ...
Page 114: ...104 G8000 Series Installation and Operation Manual FIGURE B 4 G8000 500 KVA OUTLINE DRAWING ...
Page 119: ......