UNPACKING AND CLEANING
2.1
Machine handling
⇒
Note
Lifting and moving of the machine must only be carried out using the
appropriate equipment supplied with the machine, which must be
located only in the places indicated in transport documents 300379 or
300369.
Lift the machine together with its switch cabinet by means of a pulley block
& beam or mechanical/hydraulic jacks.
With a lifting pulley block & beam:
Put four lifting bars 3, supplied with the machine, into the openings in the
base. Screw in 8 fixing screws 4 merely to keep the lifting bars from acciden-
tally slipping out of the base.
∆
Attention!
Do not tighten the bolts. Leave 0.5–1.5 mm play between the screw
heads and the lifting bar flange.
Slip 2 ties 5 on 2 bars 3 and into axes 18 of the switch cabinet. Screw tie nuts
9 to bring the switch cabinet close to the machine and support it.
Hitch lifting slings 6 round all bars 3 and at lifting beam 7. Put wooden wedges
between the slings and enclosure 8 to protect the latter. Fit the horizontal
door–handles in place. Lift the machine slowly; 2 beams inside the base also
support the switch cabinet.
With a mechanical / hydraulic jack:
Put 4 jacks under lifting bars 3. Lift the machine together with the switch cabi-
net. Slide 2 or 3 roller flats underneath to facilitate transport.
⇒
Note.
The lifting and handling equipment (function 8910 of technical descrip-
tion 300429 for M
ULTI
DECO 26/6 or 300519 for M
ULTI
DECO 32/6) may
be returned to TORNOS S.A. after use.
Replace the coolant tank, the conveyor, the MAYFRAN tank, reconnect the
tubes.
Stabilise back plate 27 by fixing it with the 2 M24 screws of the coolant tank.
Fit the barguide and level it by means of the 3 levelling elements of its rear
support.
∆
Attention!
The machine must not be operated with open doors and guards.
Before switching the machine on and starting up, make sure that all
doors, access doors and other guards are properly closed.
The switch cabinet is attached to the frame with 2 M16 bolts, situated down
in the cabinet and accessible through its door on the side of Main Switch QS0.