12
Note
It must be ensured that the heat storage blocks are installed flush with
the edge of the housing at the sides and the rear and thatno great gap
between the storage stones is created.
Note
It`s important that the flue pipe connection and the cleaning opening
must be tightly. This also applies the transitions between nozzles to
chimney and flue pipe to ceiling connection or wall connection.
10. Slide the flue gas baffle
plate in from above
11. Insert the front storage plate and refit the
start-up flap at the top
12. Test the function of the start-up flap
13. Refit the storage cover and ensure that the seal is positioned correctly