© The Stone Bake Oven Company 2014. All rights reserved.
Stage 11
Place the flue length into the oven. You can use a different
flue configuration if preffered, see the next step for an
example.
3D Impression
NOT TO SCALE
Stage 10
Place the dome onto the base of the oven,
no mortar is needed to bed this although can
be used if you require. Using a damp sponge,
generously dab water on the joint line in the oven
dome. Generously apply fire cement to fill the
joint lines in the oven dome surface. Do not fill
inside the oven. Once the fire cement is applied,
check the seal of the oven by lighting a small fire
with two pieces of newspaper. Check for smoke
leaks, if so, fire cement the gap.
3D Impression
NOT TO SCALE
Please note that it is optional to have the
bends in the flue system, a standard straight
500mm length flue is standard practice, this
just gives you a different aesthetic finish.
Using a saw, trim off the excess calcium silicate board as
shown in the diagram above.