TPV Rubber Pad Installation (Only applicable to TPV Rubber Substitution)
TPV
Rubber pad is to be slid onto the flanges of the base rails following the rubber
coverage requirement from the Construction Package. To ensure the rubber slides on
properly, the tilt assemblies must be installed first, and the rail should be flipped upside
down for ease of sliding. Best practice is to use a sawhorse for the tilt assemblies & the
rubber pads as the first step of the installation.
Typical coverage is 30” pcs of the TPV Pad spaced 12” apart.
1) Flip Base
Rail over
2) Slide Rubber
on to Base Rail
Roof warranty holder should be contacted to ensure compatibility with the roof membrane and ensure the roof warranty
is maintained, if applicable.
Typical coverage is 30" pcs of the rubber pad spaced 30" apart. If any part of the base rail is contacting the roof in
locations without the rubber pad, shift the rubber pad accordingly to protect contact points ensuring that a minimum of
3" has been left for drainage.
Ensure that all edges of the base rail are protected by the rubber pad.
Alternative rubber coverage can be accommodated at customer's request.