6.4 Ballast Installation
Secure blocks with the provided ballast clamp in the appropriate locations according to
the ballast plan on the Construction package. Please refer to the ballast block drawing
for further information located in the Construction Package.
TGR Assembly with Ballast
Ballast Tray Alternative
If ballast trays are required utilize the configurations below corresponding to the ballast
plan of the Construction package.
6.5 Home Run Wiring
After top rail installation is complete, this would be the best time to run all PV cable and
home runs as this allows the installer to have free range of access to the racking for
securing the PV cable.