NOTE:
Must be hard wired, no plug allowed.
For your safe use in winter, it’s strongly recommended to equip heating priority function.
For the detailed wiring diagram, please refer to Appendix 1.
3. Options for protecting devices
MODEL
AXCR10 AX
Breaker
Rated Current A
12.0
Rated Residual
Action Current mA
30
Fuse A
12.0
Power Cord
(
mm
2
)
3×2.5
Signal cable
(
mm
2
)
3×0.5
NOTE: The above data is adapted to power cord ≤ 10m.If power cord is
increased. The signal cable can be extended to 50m at most.
2.3. Trial after installation
Please check all the wirings carefully before turning on the heat pump.
2.3.1
.
Inspection before use
Check installation of the whole heat pump and the pipe connections according to the pipe
connecting drawing;
Check the electric wiring according to the electrical wiring diagram and earthing connection;
Make sure that the main power is well connected;
Check if there is any obstacle in front of the air inlet and outlet of the heat pump
2.3.2
.
Trial
The user is advised to start the water p
Distribution Box(Customer prepare)
Power Supply
400V 50Hz
Breaker
Earthing
15
Must be hard wired, no plug allowed.
For your safe use in winter, it’s strongly recommended to equip heating priority function.
For the detailed wiring diagram, please refer to Appendix 1.
and cable specification
AXCR13 AXCR17 AXCR21 AXCR28 AXC
15.0
19.0
22.5
24.5
28.5
30
30
30
30
30
15.0
19.0
22.5
24.5
28.5
3×2.5
3×4
3×4
3×6
3×
3×0.5
3×0.5
3×0.5
3×0.5
3×0.5
NOTE: The above data is adapted to power cord ≤ 10m.If power cord is
>
10m, wire diameter must be
increased. The signal cable can be extended to 50m at most.
Please check all the wirings carefully before turning on the heat pump.
Check installation of the whole heat pump and the pipe connections according to the pipe
according to the electrical wiring diagram and earthing connection;
Make sure that the main power is well connected;
Check if there is any obstacle in front of the air inlet and outlet of the heat pump
The user is advised to start the water pump before the heat pump, and turn off the heat pump
Distribution Box(Customer prepare)
Power Cord
Swimming Pool Heat Pump Wiring Board
Fuse
For your safe use in winter, it’s strongly recommended to equip heating priority function.
CR28T AXCR35T AXCR40T
28.5
11.3
15.0
30
30
30
28.5
11.3
15.0
3×6
5×2.5
5×2.5
3×0.5
3×0.5
3×0.5
10m, wire diameter must be
Check installation of the whole heat pump and the pipe connections according to the pipe
according to the electrical wiring diagram and earthing connection;
Check if there is any obstacle in front of the air inlet and outlet of the heat pump
ump before the heat pump, and turn off the heat pump
Swimming Pool Heat Pump Wiring Board