ver.2
54
2.
To provide the conditions of the equipment putting into service according to its type and
features, in the following manner:
- assembling, connection of the installation and tightness and pressure test executed by
authorized staff
- loading the installation and airing it
- connecting to the electrical mains
- providing the technical conditions of burned gases exhaust
3.
To obtain all the necessary documents and approvals for authorizing the equipment
operation according to the legal provisions in force; for certain equipments, the buyer will
pay all the taxes charged by the authorities in the field (i.e. ISCIR) in order to authorize its
operation.
4.
Both for putting into service and for making the interventions, revisions or verifications, the
buyer will permit the acces of the service company personnel to the location where the
equipment is assembled, including to all the documentation that certifies that all the legal
approvals for the certification of the operation have been obtained.
II
. Service company obligations
1.
The putting into service will be achieved by the
service company
authorized by
S.C.
Termofarc S.R.L.
and this has the following duties:
- to verify the correctness of the equipment assembling (according to the assembling instructions
in the technical book of the product and to the applicable legal provisions).
- To verify the efficiency of the safety devices
- to check the necessary documents demanded by the law and by the producer in order to
authorize the operating of the equipments (
if applicable).
- to make the necessary adjustments for the operation within the best parameters
- to turn on the equipment and to heat test it
- to verify the operation of the equipment within the parameters according to the technical
book of the equipment.
- to train the user to adequately use and maintain the equipment.
- to draw up
the report of putting into service
or
the report of verifications, trial and
tests for the authorization of the putting into service.
2.
The verifications made by the service operator concern only the good operation of the
equipment that is to be put into service. Any irregularity found at the installation to which it
is connected will be registered in “Report of verifications, trial and tests for the
authorization of the putting into service”.
3.
When
the service operator
finds, after the check, certain irregularities that might affect
the
proper and safe operation
of the equipment, the buyer will refuse the putting into service
until the buyer corrects such irregularities. The found irregularities will be mentioned in
the
tests report for the authorization of the putting into service
.
4.
S.C. Termofarc S.R.L.
will exonerate of any responsibility concerning the eventual
damages caused by the putting into service and exploiting of the the equipment by unskilled
or unauthorized personnel or beyond the legal provisions and of the technical prescriptions
in force stipulated by the manufacturer in the technical book of the product and by the law.
III
. Warranty exclusions:
WARRANTY CONDITIONS
Summary of Contents for FI-100NSP
Page 9: ...ver 2 9 Each boiler has its own identification plate IDENTIFICATION fig 1 ...
Page 12: ...ver 2 12 Side view Front view fig 5 fig 4 TECHNICAL DATA fig 6 fig 7 1 ...
Page 13: ...ver 2 13 fig 7 2 fig 7 3 TECHNICAL DATA ...
Page 34: ...ver 2 34 2 3 Burner s circuit diagram PELLETS BURNER fig 25 ...