PUTTING INTO SERVICE
Do not forget: The operations of first putting into service are mandatory and will be
executed by qualified personnel, certified by ISCIR.
3.1. The first putting into service
3.1.1. Checks during the first putting into service
When putting into service the boiler for the first time, the following will be checked and
observed:
- respecting the boiler assembling conditions and the requirements to be fulfilled in the plant
room.
- existence and correct choice of the bleeders and their correct connection.
- existence and correct dimensioning of the open or closed expansion tanks (as applicable) and
the correct connection of the connecting pipes between the boiler and the expansion tank;
- verifying the existence and the correct connection of the cooling coil with heat valve.
- verifying the electrical connection to the earthing plug
- the correct connection to the stack ; the stack must clean, tight, not obturated and protected at
the terminal end.
- verifying the fans blowing combustion air.
- verifying the operation of the adjustment and control device.
- verifying the correct connection of the installation filling system and of the heating circuit.
- verifying whether the system is filled with water and aired.
- verifying the pressure of the air in the expansion tank and its adjustment according to the
hydrostatic pressure in the installation (for the installations with closed expansion tank)
- verifying the operation circulation pump (electrical feed, rotor’s unblocking, airing).
- verifying the tightness of the entire system.
- when the boiler reached the operating temperature the system’s tightness is checked again.
3.1.2. Putting into service
3.1.2.1. Putting into service for the wood operation
When putting into service, these are the steps to be taken in this specific order:
- the draft thermostatic controller is adjusted at the intended value of the water in the boiler; we
recommend operation values of 70 - 90 ºC.
- the fire is lighted in the boiler, by introducing through the door of the burning point paper and a
sufficient quantity of wood (chips) on the plane grate in order to form an embers layer
- after forming the embers layer the burning point is filled with wood (maximum half of the height of
the focus point) and the doors are closed;
- verifying the draft of the sstack and the temperature of the burnt gases
-verifying the tightness of the boiler’s door, of the stack and the tightness of the burned gases
route
-verifying the operation of the draft controller
- verifying the operation of the cooling coil– heat valve device
If the ignition is correct the flame is yellowish, slightly reddish and without smoke.
Attention! During the first lighting of the fire, condense appears; yet it disappears once
the boilers is heating up.
PUTTING INTO SERVICE
Summary of Contents for FI-100NSP
Page 9: ...ver 2 9 Each boiler has its own identification plate IDENTIFICATION fig 1 ...
Page 12: ...ver 2 12 Side view Front view fig 5 fig 4 TECHNICAL DATA fig 6 fig 7 1 ...
Page 13: ...ver 2 13 fig 7 2 fig 7 3 TECHNICAL DATA ...
Page 34: ...ver 2 34 2 3 Burner s circuit diagram PELLETS BURNER fig 25 ...