Perform Pre-operation Inspection
Genie specifications require that this procedure be
performed every 8 hours or daily, whichever comes
first.
Completing a Pre-operation Inspection is essential to
safe machine operation. The Pre-operation Inspection
is a visual inspection performed by the operator
prior to each work shift. The inspection is designed
to discover if anything is apparently wrong with a
machine before the operator performs the function
tests. The Pre-operation Inspection also serves to
determine if routine maintenance procedures are
required.
Maintenance
A-3
Perform Function Tests
Genie specifications require that this procedure be
performed every 8 hours or daily, whichever comes
first.
Completing the function tests is essential to safe
machine operation. Function tests are designed to
discover any malfunctions before the machine is put
into service. A malfunctioning machine must never
be used. If malfunctions are discovered, the machine
must be tagged and removed from service.
A-4
Check the Chains
Check the Chains and shackles used to fix the
Concrete Buckets and Brick-Holder Basket to the
fork carriage.