2. 

If necessary, remove three screws and reposition/realign brackets on 

sides of distribution panel, as shown in “Bracket Orientation”.

3. 

Locate an unused rack position and mount panel using four screws and 

lock washers provided, as shown in “Rack Mounting”. (Prefer mounting 

panel as high as possible on rack.) Tighten screws to 35 in.-lb (4.29 N•m).

Telect, Inc. • USA +1.509.926.6000 • 52.33.3836.37.52

www.telect.com • © 2010 Telect, Inc., All Rights Reserved, 130316-6 A0

Page 10

4. Before connecting any conductor, use a multimeter to measure the resistance between the 

input

NEG

and 

POS/RTN

 terminals at the rear corners of the panel. Expect 500

Ω

 or more for 

both Side A and Side B.

WARNING

!

WARNING! Failure to properly ground this equipment can create hazardous conditions for 

installation personnel and to the equipment.

ALERT

!

ALERT!  Only use components and crimping tools approved by agencies or certifying 

bodies recognized in your country or region such as Underwriter’s Laboratories (UL), 

TUV, etc.

5. For ground wiring, use a listed (approved) crimping tool to at-

tach a listed (approved), single- or dual-hole compression lug 

(dual hole is highly recommended) suitable for a #10 stud 
(~5 mm) on 

5

/8

-in. (15.9 mm) centers onto a suitable ground 

wire. (Ground wire can be up to #6 AWG for a dual-hole lug. 

Conductor size depends on input interruption device.)

6. Use a coarse, nonmetallic cleaning pad to clean the terminals 

and stud(s).

7. Telect recommends that you lightly coat anti-oxidant on the lug, grounding screw(s), and sur-

rounding contacting surface. 

8. Connect the lug to the rear panel using the #10 screw(s) provided, as shown in Figure 7.

WARNING

!

WARNING! Before connecting input power cables, make sure the input power to the panel 

is turned off.

9. Make sure the input power is off.
10. For input wiring — wiring used as inputs to this 

distribution panel, 
a. Crimp dual-hole compression lugs for ¼-in. studs 

on 

5

/8

-in. (15.9 mm) centers onto suitable copper 

wires (#6 to 1/0 AWG) for 

NEG

and

POS/RTN

ter-

minals, Feeds A and B. Lug width must not exceed 

0.52 in. (13.4 mm).

b. Use a coarse, nonmetallic cleaning pad to clean 

terminals and studs.

A B F

PWR

ALM

Figure 7 - Ground 

Lug Connection

Figure 8 - Compression 

Lug Inputs

WARNING!

 Failure to properly ground this equipment can create hazardous 

conditions to installation personnel and to the equipment.

WARNUNG!

 Bei unsachgemäßer Erdung besteht Gefahr für das 

 

Installationspersonal und das Gerät!

¡AVISO!

 La conexión incorrecta a tierra puede ser peligrosa tanto para los 

instaladores como para el equipo.

ADVERTISSEMENT ! 

Si vous ne reliez pas correctement cet équipement à la 

terre, son utilisation présente des dangers pour la personne qui l’installe ainsi 

que pour l’équipement

.

Bracket Orientation 

118267-2 A0

Page 3

2. If necessary, remove 3 screws and reposition/re-align brackets on sides of distri-

bution panel, as shown in “Bracket Orientation”.

3. Locate an unused rack position and mount panel using 4 screws and lockwash-

ers provided, as shown in “Rack Mounting”. (Prefer mounting panel as high as

possible on rack.) Tighten screws to 35 in.-lb (4.29 N•m).

WARNING

!

WARNING! Failure to properly ground this equipment can create haz-

ardous conditions to installation personnel and to the equipment.
WARNUNG! Bei unsachgemäßer Erdung besteht Gefahr für das Instal-

lationspersonal und das Gerät!
¡AVISO! La conexión incorrecta a tierra puede ser peligrosa tanto para

los instaladores como para el equipo.
ADVERTISSEMENT ! Si vous ne reliez pas correctement cet équipe-

ment à la terre, son utilisation présente des dangers pour la personne

qui l'installe ainsi que pour l'équipement.

ALERT

!

ALERT! Only use components and crimping tools approved by agencies or

certifying bodies recognized in your country or region such as Underwriter’s

Laboratories (UL), TUV, etc.

4. For ground wiring, use a listed (approved) crimping tool to attach a listed (ap-

proved), single- or dual-hole compression lug onto suitable ground wire. (Use

#10 to #6 AWG, depending on input interruption device.)

5. Use a coarse, nonmetallic cleaning pad to clean terminals and stud(s).
6. Telect recommends that you lightly coat anti-oxidant on lug, grounding terminal,

and surrounding contacting surface. Connect lug to stud using M5 washer and

nut from terminal, as shown in “Ground Lug Connection”. Tighten nut to 20 in.-lb

(~2.25 N•m) using a 8 mm (

5

/16

in.) socket.

WARNING

!

WARNING! Before connecting input power cables, make sure input

power to panel is turned off.
WARNUNG! Vor Anschluss der Eingangsstromkabel ist sicherzus-

tellen, dass der Eingangsstrom ausgeschaltet ist.
¡AVISO! Antes de conectar los cables de entrada de la alimentación, compruebe que la alimentación

de entrada al panel está cortada.
ADVERTISSEMENT ! Avant de connecter les câbles d'entrée d'alimentation, assurez-vous que l'ali-

mentation électrique du panneau est coupée.

7. Make sure input power is off.

Bracket Orientation

Torque #8 screws to

15 in.-lbs [1.7 N•m]

Mounting

Bracket

3-in. Offset

Position

4-in. Offset

Position

F

lush Position

Rack Mounting

Ground Lug Connection

Torque nuts to 20 in.-lb (2.25 N•m)

A

nti-oxidant

compound

Rack Mounting

ALERT! Only use components and crimping tools approved by agencies 

or certifying bodies recognized in your country or region such as 

 

Underwriter’s Laboratories (UL), TUV, etc.

Ground Lug Connection 

4. 

For ground wiring, use a listed (approved) crimping tool to attach 

 

a listed (approved), single- or dual-hole compression lug onto 

 

suitable ground wire. (Use #10 to #6 AWG, depending on input 

 

interruption device.)

5. 

Use a coarse, nonmetallic cleaning pad to clean terminals 

 

and stud(s).

6. 

Telect recommends that you lightly coat antioxidant on lug, grounding 

terminal and surrounding contacting surface. Connect lug to stud using 

M5 washer and nut from terminal, as shown in “Ground Lug Connection”. 

Tighten nut to 20 in.-lb (~2.25 N•m) using a 8 mm (5/16 in.) socket.

Telect, Inc. • USA +1.509.926.6000 • 52.33.3836.37.52

www.telect.com • © 2010 Telect, Inc., All Rights Reserved, 130316-6 A0

Page 10

4. Before connecting any conductor, use a multimeter to measure the resistance between the 

input

NEG

and 

POS/RTN

 terminals at the rear corners of the panel. Expect 500

Ω

 or more for 

both Side A and Side B.

WARNING

!

WARNING! Failure to properly ground this equipment can create hazardous conditions for 

installation personnel and to the equipment.

ALERT

!

ALERT!  Only use components and crimping tools approved by agencies or certifying 

bodies recognized in your country or region such as Underwriter’s Laboratories (UL), 

TUV, etc.

5. For ground wiring, use a listed (approved) crimping tool to at-

tach a listed (approved), single- or dual-hole compression lug 

(dual hole is highly recommended) suitable for a #10 stud 
(~5 mm) on 

5

/8

-in. (15.9 mm) centers onto a suitable ground 

wire. (Ground wire can be up to #6 AWG for a dual-hole lug. 

Conductor size depends on input interruption device.)

6. Use a coarse, nonmetallic cleaning pad to clean the terminals 

and stud(s).

7. Telect recommends that you lightly coat anti-oxidant on the lug, grounding screw(s), and sur-

rounding contacting surface. 

8. Connect the lug to the rear panel using the #10 screw(s) provided, as shown in Figure 7.

WARNING

!

WARNING! Before connecting input power cables, make sure the input power to the panel 

is turned off.

9. Make sure the input power is off.
10. For input wiring — wiring used as inputs to this 

distribution panel, 
a. Crimp dual-hole compression lugs for ¼-in. studs 

on 

5

/8

-in. (15.9 mm) centers onto suitable copper 

wires (#6 to 1/0 AWG) for 

NEG

and

POS/RTN

ter-

minals, Feeds A and B. Lug width must not exceed 

0.52 in. (13.4 mm).

b. Use a coarse, nonmetallic cleaning pad to clean 

terminals and studs.

A B F

PWR

ALM

Figure 7 - Ground 

Lug Connection

Figure 8 - Compression 

Lug Inputs

WARNING!

 Before connecting input power cables, make sure input

power to panel is turned off.

WARNUNG!

 Vor Anschluss der Eingangsstromkabel ist sicherzustellen,

dass der Eingangsstrom ausgeschaltet ist.

¡AVISO!

 Antes de conectar los cables de entrada de la alimentación, 

 

compruebe que la alimentación de entrada al panel está cortada.

ADVERTISSEMENT !

 Avant de connecter les câbles d’entrée d’alimentation, 

assurez-vous que l’alimentation électrique du panneau est coupée.

7. 

Make sure input power is off.

Torque #8 screws to

15 in.-lbs [1.7 N•m]

Mounting

Bracket

3-in. Offset 

Position

4-in. Offset 

Position

Flush Position

Torque nuts to 20 in.-lb (2.25 N•m)

Anti-oxidant

compound

Summary of Contents for T009-5 Series

Page 1: ...ompression inputs only White or black panels can be configured with any combination of 1A to 20A Carling M Series breakers oriented with the on symbol at either the bottom or top 50A thermal input bre...

Page 2: ...r dual hole lug Conductor size depends on input interruption device 20 in lb 2 25 N m max Input terminals Compressions Quantity Stud Lugs Cable Torque 4 2 BATT 2 RTN M5 with KEPS nut Use 8 mm 5 16 in...

Page 3: ...omer Service Department at 1 800 551 4567 domestic only or 1 509 926 6000 for further recourse NOTE Panel brackets provide either flush or extended EIA or WECO mounting in a 19 or 23 rack Panel is con...

Page 4: ...insi que pour l quipement ALERT ALERT Only use components and crimping tools approved by agencies or certifying bodies recognized in your country or region such as Underwriter s Laboratories UL TUV et...

Page 5: ...tighten to 14 in lb 1 5 N m Compression Lug Inputs Screw Tight Vertical Horizontal Inputs Alarm Indicators 9 Make sure power is off open breaker dummy fuse or open fuse holder at power distribution u...

Page 6: ...l breaker out puts on each side must not exceed 40A for a panel with an optional thermal input breaker 50A for a panel having screw tight inputs connectors but without an optional thermal input breake...

Page 7: ...aced Then turn off input power to that side of panel 4 Place breaker to be replaced in the off position 5 Using a very small flat tipped screwdriver carefully pry out on bottom of breaker while applyi...

Page 8: ...nting Brackets Black 090 0041 0030 White 090 0041 0031 Front Cover Clear 090 0001 0001 Designation Label 1 7 A B 115353 ALERT The LINE side connection of the breaker has live VDC Do not allow contact...

Page 9: ...is closed and C to NO is open Input Power Failure POWER ON A or POWER ON B LED s will go off POWER FAIL relay de energizes so that C to NC opens and C to NO closes Input Breaker Opens input breakers...

Page 10: ...e Inputs Wire Binding A Side Inputs Compression Inputs With 50A Input Breakers Screw Tight Horizontal Inputs Without 50A Input Breakers Compression Inputs Without 50A Input Breakers 100A max side Scre...

Page 11: ...akers Installed with On at Top 3 White Enclosure Breakers installed with On at Top Panel Color Breaker Orientation 0 Screw Tight Horizontal Inputs with 50A Thermal Input Breakers Inputs Type of Connec...

Page 12: ...r its patent rights or the patent rights of others This document and the products described herein are subject to change without notice INPUT BREAKER B BATT 24V 48V 100A MAX 24V RTN BATT RTN GND CHS C...

Reviews: