Equipment Connections
9
2.2
Rack mounting the TMP800
The TMP800 is mounted on a customer provided equipment rack using the mounting hardware
packaged in the box.
2.2.1
Prerequisites
To rackmount the TMP800, you will need:
•
One 19” customer provided equipment rack. Racks must be solidly anchored to the floor with
appropriate support at the top of the racks.
•
Climate controlled room: 0 to +50 Celsius, 0 to 95% non-condensing humidity.
2.2.2
Vertical Placement of Tmedia Equipment
The TMP800 is housed in a 1U chassis, as tabulated in Table 2.1 on page 9. It is important that you
provide for enough room on the equipment rack to allow for the installation of the TMP800 and other
related equipment. Consider the available space on your equipment rack and the individual heights of
each unit. Due to the rear-exhaust heat vents and the efficient heat dissipation design, there is no need
to leave any physical vertical space between the placement of the TMP800 on the equipment rack.
Table 2.1
Tmedia Physical Height
Tmedia Model Number
Vertical Height
TMP800
1U
Gigabit Switches
a
a. Verify the manufacturer specifications for placement and spatial requirements.
1U (or more)
Control Servers
b
b. Verify the manufacturer specifications for placement and spatial requirements. Depending upon the server that you
will use the vertical height may range beyond a 1U size.
1U (or more)