Marchesan Implementos e Máquinas Agrícolas “TATU” S.A.
GNF-E / GNFM-E
Important data
Average income table
NOTE An average speed of 9 km/h was assumed to prepare the table above.
To know how many hours will be spent to work in a certain previously known area, it
is necessary to divide the value of the area by the hourly income.
Example: An area of 100 hectares to be worked with a GNFM/E that has 120 disc
blades (Hourly income = 9.19 hectares).
So: 100 = 10.88
9.19
Approximately will be spent 10 (ten) hours to work in an area of 100 hectares.
Model
Number of
disc blades
Cutting
width (m)
Hourly
income (ha)
Daily income (ha)
GNF/E
GNFM/E
104
9.93
8.04
72.38
120
11.35
9.19
82.74
156
15.66
12.68
114.16