Section 2: Screen Hanging up in the Guide Rails 

 

A.

 

Remove panel box bottom.  

B.

 

Check operator to ensure it isn’t the reason the screen is stopping. Does the shaft continue to rotate 

after the screen stops? If the shaft does not continue to rotate, adjust the operator as necessary 

 motor 

limits, check power, engage crank rod etc.  

C.

 

Check the gap of the retention inserts with feeler gauges that can be purchased at any automotive parts 

supply store. The gap should be 0.035” to 0.040”. (or about 0.9mm to 1.0mm) 

 

D.

 

Check to ensure the shaft is centered and that the zipper of the screen runs straight into the retention 
insert, with a visual inspection. Adjust as necessary by moving the shaft from side to side by hand.  

E.

 

Check to ensure the shaft is perfectly level, by pl

acing a 4’ level on the shaft. 

 

F.

 

Ensure  no  mounting  fasteners  are  installed  through  the  guide  rail  channel.  L-build  is  required  for  all 
between jamb applications.  

G.

 

Check the A1 width against that which was ordered, in 3 places 

 top, middle and bottom, and ensure 

there is free play in the bottom profile from side to side.  

H.

 

Check to ensure the rail spacing is correct, true and plumb from top to bottom.  

I.

 

Check to ensure the rails are not twisted from installation. A straight edge or level can be placed against 
the face of the rails looking for gaps between the straight edge and the rail. Use shims behind fastening 
points where necessary. To ensure fasteners are not over-tightened, please use the clutch on your drill.  

J.

 

If this is to service an older installation: clean out the retention inserts to ensure they are not plugged 
up with debris. Use 100grit sandpaper folded over on itself to clean out the insert.  

K.

 

Once the source of the problem has been identified and resolved, operate the unit top to bottom to 
ensure smooth operation.  

 

Please note: Do not lubricate the retention system as it is not designed for this, nor should it 

 

ever need it.  

 

NEED  SUPPORT:  If  you  are  not  able  to  resolve  the  performance  issue,  contact  Talius’  Inside 

Sales team for support at 1-800-665-5550.  

 
Please be sure to provide them with:  

 

The order tag name and if this is an initial install or return visit to site  

 

Please  provide pictures or video, wherever  possible, to  help describe  the problem.  Picture  or video 
should be a close up view focused on the shaft and zipper at the point of entry into the black retention 
insert, as well as shots from a distance of the complete unit.

 

 
 

 
 

 

Summary of Contents for Habitat Screen

Page 1: ...hrough a small fraction of this booklet as it covers all types of Habitat Screen installations At the beginning of each section the booklet will point out if the section can be skipped Habitat Screens...

Page 2: ...While we do not supply common tools and hardware contact us to purchase the specialized tools like motor tester cables Please note Talius does not supply the fasteners for installation We believe this...

Page 3: ...Talius Habitat ScreenTM Installation Guide Version 2018 1 3 TALIUS PARTS OVERVIEW...

Page 4: ...necessarily aligned perfectly with the panel box so it s best to level the unit based upon the shaft 1 2 Guide Rails Both guide rails must be mounted plumb and true with equal spacing between from top...

Page 5: ...ant to ensure that there is an even plane on which to mount the Habitat Screen Face of Wall mounted Habitat Screens come with 7 8 build up for the guide rails and panel box top to allow for bottom pro...

Page 6: ...ll a pilot hole of approximately 3 8 10mm in diameter through the wall being sure to follow the same pitch as observed above Have a helper safely hold a piece of wood over the location the hole will e...

Page 7: ...he guide rail 4 1b Between Jamb Mount Applications Guide rails will not be pre drilled unless your unit has rails that will be recessed into a post and fastened through channel and you have requested...

Page 8: ...tion and hold the unit over the opening where you wish it to be located Install the top screw in one of the guide rails Using a 4 level and ensuring the bubble is perfectly centered between the lines...

Page 9: ...plate to be placed underneath the universal joint to provide a stronger mounting base This is a common point of failure if a secure fastening is not accomplished in the initial install If the operato...

Page 10: ...see a simple design in the motor configuration but this is wrong The description supplied with this job does not contain enough information to explain the intricacies of a tubular motor and it cannot...

Page 11: ...nel power must be disconnected to additional units so that only the unit being adjusted has power After isolating a single unit preform the limit adjustment steps below and repeat for each unit Step O...

Page 12: ...buttons on the head of the motor see diagrams below 2 Using the tester cables or switch operate the unit up until curtain stops at the temporary UP limit set by Talius 3 Unlock the UP limit switch on...

Page 13: ...h has cut off power and will restore it automatically in 10 to 45 minutes depending on the surrounding temperature Motors are designed to run for short intervals only During limit switch adjustments t...

Page 14: ...wall Secure each end plate with at least one 2 3 50 76mm long screw dependent upon what is suitable for the mounting surface For units in high wind installations use two fasteners per end plate as sho...

Page 15: ...ions install a bottom stop into each guide rail 9 3 Caulking Caulking around the top of the panel box and guild rails will help to prevent water from penetrating behind the Habitat Screen and to ensur...

Page 16: ...ow sufficient room for maneuvering the bottom profile into position As such any fasteners holding the box to the wall will have to be removed I Check to see if the fabric is tracking properly by opera...

Page 17: ...side H Check to ensure the rail spacing is correct true and plumb from top to bottom I Check to ensure the rails are not twisted from installation A straight edge or level can be placed against the f...

Reviews: