English
19
VH
11.4. OPERATING CHECK LIST
11.4.1. GENERAL
1.
Before initial start up, be sure that the fan wheel is rotating free on it shaft.
2.
Make sure that the filter is correctly positionned on its bracket.
3.
Ensure that all hydraulic connections are tightened correctly.
4.
Cheek for any unusual noises or vibration in the running components.
5.
Check that the condensates drainage hose is connected and allows liquid to drain freely.
Check that condensates actually drain properly (installation with or without drainage pump) by
pouring water into the condensates tray (pump electricity supply switched on).
11.4.2. ELECTRICAL
²
Ensure that all electrical connections are tightened correctly.
11.4.2.1. OPERATING VOLTAGE:
²
Recheck voltage at unit supply terminals.
11.4.2.2. CONTROL
1.
Operate system and thermostat switches.
2.
Check unit is wired for correct control of unit fan, cooling and heating modes.
11.4.3. FINAL CHECK
1.
All panels and fan guards are in place and secured.
2.
Unit clean and free of remainder installation material.
12. FINAL TASKS
If needed, fix the cables and the pipes on the wall with clamping collars.
Operate the air conditioner in the presence of the user and explain all functions.
Show him how to remove, clean and place back the filters.
Summary of Contents for VH07
Page 2: ......
Page 25: ...APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO...
Page 42: ...XVIII VH APPENDIX ANNEXE ANLAGE ALLEGATO ANEXO...
Page 43: ......