[5.3] Secure The Detector Housing To The Duct

Slide the foam gaskets over the tube bushings as shown in
Figure 3. Use the two machine screws to screw the detector
housing to the duct.
CAUTION: Do not overtighten the screws.

Figure 3. Installation of foam gaskets over sampling

tube bushings:

A78-2045-00

[5.4] Sampling Tube Installation of Ducts Greater

Than 1

1

/

2

 Feet Wide

The sampling tube is identified by a series of air inlet holes
on the tube. One telescoping tube is included for ducts up
to 18

 in width. All other lengths must be purchased sepa-

rately. Order the correct length, as specified in Table 1, for
width of the duct where it will be installed. The exhaust
tube is molded onto the base of the duct housing, and the
A2440-00 Exhaust Tube Extension is available as an acces-
sory in those cases where the molded exhaust port does not
extend at least 2 inches into the duct.

The inlet tube is always installed with the air inlet holes
facing into the air flow. To assist proper installation, the
tube’s mounting flange is marked with arrows. Make sure
the inlet tube is mounted so that the arrows point into the
air flow (see Figure 4). Figure 5 shows the various combi-
nations of tube mounting configurations with respect to air
flow. Mounting the detector housing in a vertical orienta-
tion is acceptable, provided that the air flows directly into
the sampling tube holes as indicated in Figure 4.

Table 1. Inlet tubes required for different duct

widths:

Outside Duct Width

Inlet Tube Required

1 to 2 ft.

ST-1.5

2 to 4 ft.

ST-3

4 to 8 ft.

ST-5

8 to 12 ft.

ST-10

[5.4.1] Installation For Ducts Greater Than 1 

1

/

2

 Feet

But Less Than 8 Feet Wide

1.

If the tube is longer than the width of the air duct,

 drill a

3

/

4

-inch hole in the duct opposite the hole already cut for

the inlet tube. Make sure the hole is 1

 to 2

 below the in-

let hole on the opposite side of the duct to allow for mois-
ture drainage. 

If the tube is shorter than the width of the air

duct,

 install the end plug into the inlet tube as shown in

Figure 4. Sampling tubes over 3 ft. long must be supported
at the end opposite the duct detector.

2. Slide the tube into the housing bushing that meets the

air flow first. Position the tube so that the arrows point
into the air flow.

3. Secure the tube flange to the housing bushing with two

#6 self-tapping screws.

4. For tubes longer than the width of the air duct, the tube

should extend out of the opposite side of the duct. If
there are more than 2 holes in the section of the tube ex-
tending out of the duct, select a different length using
Table 1. Otherwise, trim the end of the tube protruding
through the duct so that 1

 to 2

 of the tube extend out-

side the duct. Plug this end with the end plug and tape
closed any holes in the protruding section of the tube. Be
sure to seal the duct when the tube protrudes.

Figure 4. Air duct detector inlet sampling tube:

INLET
TUBE
END
PLUG

AIR HOLES

ARROWS

MUST FACE

INTO AIR FLOW

AIR FLOW DIRECTION

FLANGE

A78-2047-00

Figure 5. Tube mounting configurations with varying

air flow direction:

AIR FLOW

DIRECTION

DUCT
DETECTOR
HOUSING

DOTS INDICATE POSITION OF

SAMPLING TUBE HOLES

AIR FLOW

DIRECTION

DUCT
DETECTOR
HOUSING

INLET

TUBE

EXHAUST

TUBE

AIR FLOW

DIRECTION

EXHAUST

TUBE

INLET

TUBE

INLET

TUBE

EXHAUST

TUBE

DUCT
DETECTOR
HOUSING

AIR FLOW

DIRECTION

EXHAUST

TUBE

INLET

TUBE

DUCT
DETECTOR
HOUSING

A.

B.

C.

D.

NOTE: Orientations C and D apply only to metal sampling tubes.

D100-67-00

3

I56-1148-04

A78-1812-08

Summary of Contents for Innovair DH100

Page 1: ...etc These actions can facilitate the management of toxic smoke and fire gases throughout the areas served by the duct system DH100 detectors are designed to operate with 12 or 24 VDC UL listed compatible 2 wire control panels Alarm current must be limited to 100mA or less by the control panel Auxiliary relay contacts for control purposes are not available for use with the DH100 Control must ini ti...

Page 2: ...pling tube end plug 11 One telescoping sampling tube 12 One 8 self tapping screw for the telescoping sampling tube NOTE For ducts over 11 2 feet longer inlet sampling tubes must be ordered to complete the installation They must be the correct length for the width of the duct where they will be installed See Table 1 on page 3 to determine the inlet tube required for different duct widths 5 Installa...

Page 3: ... Than 8 Feet Wide 1 If the tube is longer than the width of the air duct drill a 3 4 inch hole in the duct opposite the hole already cut for the inlet tube Make sure the hole is 1 to 2 below the in let hole on the opposite side of the duct to allow for mois ture drainage If the tube is shorter than the width of the air duct install the end plug into the inlet tube as shown in Figure 4 Sampling tub...

Page 4: ...nside the duct may cause excessive vibration especially when the longer sampling tubes are used In these cases a 3 inch floor flange available at most plumbing supply stores may be used to fasten the sampling tube to the other side of the duct When using the flange connector mounting technique drill a 1 to 11 4 inch hole where the flange will be used 5 4 3 Modifications of Inlet Sampling Tubes The...

Page 5: ...Smoke Detector Maintenance And Test Procedures Test and maintain duct smoke detectors as recommended in NFPA 72 The tests contained in this manual were devised to assist main tenance personnel in verification of proper detector operation Before conducting these tests notify the proper authorities that the smoke detection system will be temporarily out of service Disable the zone or system under te...

Page 6: ... INITIATION LOOP EOL RESISTOR SPECIFIED BY PANEL MANUFACTURER CAUTION Do not loop wire under terminals when wiring detectors Break wire runs to provide system supervision of connections 1 2 3 4 5 6 7 3 4 5 Test Test Reset Reset Test Reset RA RA V Out V In 8 7 8 V In V Out V In V In V Out DH100 RTS451 KEY 6 2 1 Alarm LED No Connection Panel Figure 8 Wiring diagram for RTS451 RTS451KEY Remote Test S...

Page 7: ...ing Procedures Notify the proper authorities that the smoke detector sys tem is undergoing maintenance and that the system will temporarily be out of service Disable the zone or system undergoing maintenance to prevent unwanted alarms and possible dispatch of the fire department 7 1 Air Filters 1 Turn off power to the system 2 Remove and inspect sampling tube filters 3 If filters are heavily coate...

Page 8: ...he obligations or limitations of this Warranty The Company s obligation of this Warranty shall be limited to the repair or re placement of any part of the air duct smoke detector which is found to be defective in materials or workmanship under normal use and service dur ing the three year period commencing with the date of manufacture After phoning System Sensor s toll free number 800 SENSOR2 736 ...

Reviews: